Need help with Daily Resource Loading for Production Elements (DAX to calculate load per day)

Hello, 

From our ERP system I have data on:
[Resource Name] (Machine Centre)
[Project Name]
[Start Date]
[End Date]
# of [Hrs of Work] required

I am trying to make a stacked bar chart that shows each day, with a slicer to filter per [Resource Name], showing which projects are being processed on on the days shown. 

Right now I can make a stacked bar with all of the work showing up on the [End Date], but what I need to do is divide the [Hours of work] between the [start date] and the [end date], thus showing how much work is to be done on each project per day.

Thanks,  

1 ACCEPTED SOLUTION
amitchandak
Super User
Super User

@nick_SMTC , refer if the blog or my file on similar topic attached after signature can help


https://community.powerbi.com/t5/Community-Blog/How-to-divide-distribute-values-between-start-date-o...

 

 

Full Power BI Video 20 Hours YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

View solution in original post

3 REPLIES 3
amitchandak
Super User
Super User

@nick_SMTC , refer if the blog or my file on similar topic attached after signature can help


https://community.powerbi.com/t5/Community-Blog/How-to-divide-distribute-values-between-start-date-o...

 

 

Full Power BI Video 20 Hours YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

Thanks amitchandak, 

 

 I was able to get the solution to work with some fine tuning. Top graph is what I had before and bottom graph is what I was able to cut it into in terms of daily resource use.  Much appreciated!!

nick_SMTC_0-1619136856438.png

 

Thanks amitchandak, got the date table working but having trouble with the formulas to assign a volume of work per date. Will continue to work on. 

Helpful resources

Announcements
Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code FABINSIDER for a $400 discount!

FebPBI_Carousel

Power BI Monthly Update - February 2025

Check out the February 2025 Power BI update to learn about new features.

March2025 Carousel

Fabric Community Update - March 2025

Find out what's new and trending in the Fabric community.