Forum Discussion
nick_SMTC
5 years agoFrequent Visitor
Need help with Daily Resource Loading for Production Elements (DAX to calculate load per day)
Hello, From our ERP system I have data on: [Resource Name] (Machine Centre) [Project Name] [Start Date] [End Date] # of [Hrs of Work] required I am trying to make a stacked bar chart that...
- 5 years ago
amitchandak
5 years agoSuper User
- nick_SMTC5 years agoFrequent Visitor
Thanks amitchandak, got the date table working but having trouble with the formulas to assign a volume of work per date. Will continue to work on.
- nick_SMTC5 years agoFrequent Visitor
Thanks amitchandak,
I was able to get the solution to work with some fine tuning. Top graph is what I had before and bottom graph is what I was able to cut it into in terms of daily resource use. Much appreciated!!