Need help with Daily Resource Loading for Production Elements (DAX to calculate load per day)

Hello, 

From our ERP system I have data on:
[Resource Name] (Machine Centre)
[Project Name]
[Start Date]
[End Date]
# of [Hrs of Work] required

I am trying to make a stacked bar chart that shows each day, with a slicer to filter per [Resource Name], showing which projects are being processed on on the days shown. 

Right now I can make a stacked bar with all of the work showing up on the [End Date], but what I need to do is divide the [Hours of work] between the [start date] and the [end date], thus showing how much work is to be done on each project per day.

Thanks,  