Hi Community
I really need your help on how to create a calendar that automatically knows that when it comes to the beginning of 2021, this is still week 53 and not week 1. I have only managed to create a calendar where the week number starts by 1 when entering a new calendar year. But for year 2021: the 1st to the 3rd january is week 53 and then week 1 starting from january 4th.
@PowerQuery @calendar@weeknum
How do i build in this knowledge ??
I rellay hope that someone has the answer to this, t
Solved! Go to Solution.
Hi @micjensen ,
This is very complex logic to code into Power Query.
I would recommend using WEEKNUM([Date], 21) in a DAX calculated column to be honest:
Pete
Proud to be a Datanaut!
Please see this article with a good way to handle that.
445 Calendar with 53-Week Years – Hoosier BI
Pat
To learn more about Power BI, follow me on Twitter or subscribe on YouTube.
Here's a custom function in M code for calculating the ISO Weeknumber (if that is what you want):
//fxISOWeekNum
(theDate as date) =>
let
a = Date.AddDays(theDate,-1),
b = Date.DayOfWeek(a,Day.Sunday),
c = Date.AddDays(theDate,-b + 3),
d2 = #date(Date.Year(c),1,3),
IWN = Number.IntegerDivide(Number.From(theDate)-Number.From(d2) + Date.DayOfWeek(d2)+6,7)
in
IWN
Please look Function for ISO Year/Week number (ISO 8601))
NB! Pay attention to offsetindays parameter (by default it equals to zero - it means week starts on Sunday)
Here's a custom function in M code for calculating the ISO Weeknumber (if that is what you want):
//fxISOWeekNum
(theDate as date) =>
let
a = Date.AddDays(theDate,-1),
b = Date.DayOfWeek(a,Day.Sunday),
c = Date.AddDays(theDate,-b + 3),
d2 = #date(Date.Year(c),1,3),
IWN = Number.IntegerDivide(Number.From(theDate)-Number.From(d2) + Date.DayOfWeek(d2)+6,7)
in
IWN
Please see this article with a good way to handle that.
445 Calendar with 53-Week Years – Hoosier BI
Pat
To learn more about Power BI, follow me on Twitter or subscribe on YouTube.
Hi @micjensen ,
This is very complex logic to code into Power Query.
I would recommend using WEEKNUM([Date], 21) in a DAX calculated column to be honest:
Pete
Proud to be a Datanaut!
Check out the April 2026 Power BI update to learn about new features.
If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.
| User | Count |
|---|---|
| 7 | |
| 5 | |
| 4 | |
| 4 | |
| 3 |