Hi All,

 

I have been struggling quite a bit lately with my refreshes failing, is it possible that having different datasets refresh too close to each other could cause this?  If it makes a difference, everything is being pulled from Excel and there are files that present in multiple datasets.

 

Thanks!!

Jim

1 ACCEPTED SOLUTION
GilbertQ
Super User
Super User

Hi @Jim_

 

Is the error a timeout error? 

And are you using the Personal On-Premise Data Gateway, or the Enterprise On-Premise Data Gateway?

Have you got the latest version installed?

 

I would suggest first testing the refresh manually, by using the Refresh Now option from the dataset. Wait for that to complete and see how long it takes.

 

Only once it can refresh successfully manually would I then look into scheduling the refresh. 

Also remember that with Power BI Pro, there are only 8 refreshes a day, or 48 with Power BI Premium.

 

If it is still failing, I would then look into where you have got the Gateway installed. 

Ensure that you have got enough CPUs (As I have found when processing Excel files, if there are a lot of applied steps in the Query Editor, it will consume almost all the CPUs).

Also ensure that you have got enough memory, as all the Query Editor steps are applied where the Gateway is installed.

And finally ensure that there is enough bandwidth, with a consistant connection to upload the data to the Power BI Service.





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!







Power BI Blog

View solution in original post

3 REPLIES 3
GilbertQ
Super User
Super User

Hi @Jim_

 

Is the error a timeout error? 

And are you using the Personal On-Premise Data Gateway, or the Enterprise On-Premise Data Gateway?

Have you got the latest version installed?

 

I would suggest first testing the refresh manually, by using the Refresh Now option from the dataset. Wait for that to complete and see how long it takes.

 

Only once it can refresh successfully manually would I then look into scheduling the refresh. 

Also remember that with Power BI Pro, there are only 8 refreshes a day, or 48 with Power BI Premium.

 

If it is still failing, I would then look into where you have got the Gateway installed. 

Ensure that you have got enough CPUs (As I have found when processing Excel files, if there are a lot of applied steps in the Query Editor, it will consume almost all the CPUs).

Also ensure that you have got enough memory, as all the Query Editor steps are applied where the Gateway is installed.

And finally ensure that there is enough bandwidth, with a consistant connection to upload the data to the Power BI Service.





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!







Power BI Blog

@GilbertQ  Thank you for the input.  I do have a substantial amount work being done in the query editor.  Although these files previously had updated reliably and there have been no changes to the query editor, there may have been some changes to the server that the personal gateway lives on. 

 

I will go through the query editor steps and see what can be done in DAX vs M to reduce the load on the server.

 

 

Hi @Jim_

 

Also see if possible to reduce the applied steps? As that could also possibly help.





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!







Power BI Blog

Helpful resources

Announcements
FabCon and SQLCon Barcelona 2026

FabCon & SQLCon – Barcelona 2026

Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.

Fabric Community Sticker Design Challenge Barcelona Carousel

Fabric Community Sticker Challenge - Barcelona 2026

If you love stickers, then you will definitely want to check out our community sticker challenge, Barcelona edition!

July Power BI Update Carousel

Power BI Monthly Update - July 2026

Check out the July 2026 Power BI update to learn about new features.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.