Hi,
I am reporting on project schedules from Project Online. There is a lot of task information that isn't available in the standard ODATA connection. I have managed to discover where task predecessor and successor information is stored and imported that. This gives me task lead and lag informatin as well as dependencies.
I also need task constraint information - that is, whether tasks have Start No Earlier than, Finisish No Ealier than (etc) constraints, and if so, what the associated dates are.
I have found nothing myself, and no search results match what I'm looking for. Has anyone managed to import this information into Power BI?
Hi @Wellingtoon ,
See if these samples and blogs are helpful.
#ProjectServer #ProjectOnline highlight report example #PS2013 #SP2013 #Excel #BI #Office – Modern W...
#ProjectServer #ProjectOnline example report #PS2013 #SP2013 #Office365 #BI #Excel #PowerPivot – Mod...
Getting started with #ProjectOnline Part 9 #PS2013 #Office365 #Project #PPM #SharePointOnline #PM #S...
URL Conventions (OData Version 3.0) · OData - the Best Way to REST
Best Regards,
Gao
Community Support Team
If there is any post helps, then please consider Accept it as the solution to help the other members find it more quickly.
If I misunderstand your needs or you still have problems on it, please feel free to let us know. Thanks a lot!