Forum Discussion
Project Online task constraint information
Hi,
I am reporting on project schedules from Project Online. There is a lot of task information that isn't available in the standard ODATA connection. I have managed to discover where task predecessor and successor information is stored and imported that. This gives me task lead and lag informatin as well as dependencies.
I also need task constraint information - that is, whether tasks have Start No Earlier than, Finisish No Ealier than (etc) constraints, and if so, what the associated dates are.
I have found nothing myself, and no search results match what I'm looking for. Has anyone managed to import this information into Power BI?
1 Reply
- AnonymousNot applicable
Hi Wellingtoon ,
See if these samples and blogs are helpful.
#ProjectServer #ProjectOnline highlight report example #PS2013 #SP2013 #Excel #BI #Office – Modern Work Management – Project and the Power Platform blog (wordpress.com)
#ProjectServer #ProjectOnline example report #PS2013 #SP2013 #Office365 #BI #Excel #PowerPivot – Modern Work Management – Project and the Power Platform blog (wordpress.com)
Getting started with #ProjectOnline Part 9 #PS2013 #Office365 #Project #PPM #SharePointOnline #PM #SP2013 – Modern Work Management – Project and the Power Platform blog (wordpress.com)
URL Conventions (OData Version 3.0) · OData - the Best Way to RESTBest Regards,
Gao
Community Support TeamIf there is any post helps, then please consider Accept it as the solution to help the other members find it more quickly.
If I misunderstand your needs or you still have problems on it, please feel free to let us know. Thanks a lot!How to get your questions answered quickly -- How to provide sample data in the Power BI Forum -- China Power BI User Group