how to ditribute data model creation task in power bi among 3 developers? data model would be based on 15 dimensions and two fact tables. I am confused whether one person should do data model or all three? if i give work to one person then what 2 person will do?

1 ACCEPTED SOLUTION

If your question is regarding timings, you have a séquentiel order.  First, conceptual model design to be done by 2/3 modelers (outside pbi) , second, the creation of the model by 1 développer, third testing/enhacements/documention by à second dev when the work of dev 1 is complète.

How ? You have different options : Shared pbix or pbip between dev or using Tabular Editor connected to xmla.

 

If it answers your query please mark my solution as the solution




Did I answer your question? Mark my post as a solution!
Appreciate your Like/Kudos

Proud to be a Super User!




View solution in original post

5 REPLIES 5
Alex87
Solution Sage
Solution Sage

You can have only 1 dev to do all the work, that's the most common dev type, but in your case you have 3 available devs. My idea is to use at least 2 dev to make the best data model possible. People tend to under evaluate the importance of a good data model. Having a co-dev for the data model, for a me a good approach in your case. 




Did I answer your question? Mark my post as a solution!
Appreciate your Like/Kudos

Proud to be a Super User!




Hi @Alex87 ,

 

how 2 dev will work on same data model?

If your question is regarding timings, you have a séquentiel order.  First, conceptual model design to be done by 2/3 modelers (outside pbi) , second, the creation of the model by 1 développer, third testing/enhacements/documention by à second dev when the work of dev 1 is complète.

How ? You have different options : Shared pbix or pbip between dev or using Tabular Editor connected to xmla.

 

If it answers your query please mark my solution as the solution




Did I answer your question? Mark my post as a solution!
Appreciate your Like/Kudos

Proud to be a Super User!




Alex87
Solution Sage
Solution Sage

my recommendation would be to have the 3 developers work together to frame the conceptual model and best practices to put in place to answer the reporting needs (harvest collective intelligence). 1 will build the model, another will be in charge of testing, ajustments (referential integrity, Power Query modif etc) and documentantation, the third person can start working on the visual reporting or if you have specific developpers for the front end, ensure the tight connection to that person.




Did I answer your question? Mark my post as a solution!
Appreciate your Like/Kudos

Proud to be a Super User!




Hi @Alex87 , how 2 person work on same data model as you meantioned 1 will build the data model and another will be charge of testing , as per my understanding both shuld be done by only 1 person

Helpful resources

Announcements
FabCon and SQLCon Barcelona 2026

FabCon & SQLCon – Barcelona 2026

Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.

60 days of Data Days Carousel

Data Days 2026

Join Fabric Data Days 2026: 60 days of free live/on-demand sessions, challenges, study groups, and certification opportunities.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.