Hi,

 

I am trying to recreate a formula field that is currently used in my Crystal Reports and turn it into a measure in Power BI.

 

The formula field in Crystal is currently:-

 

if {urvPMContractAnalysisDD_WithPCOEstCost.Mth} < {?CurrentPeriodStart} then
if {urvPMContractAnalysisDD_WithPCOEstCost.ProjMth} < {?CurrentPeriodStart} then
{urvPMContractAnalysisDD_WithPCOEstCost.ProjDollars}
else
{urvPMContractAnalysisDD_WithPCOEstCost.ContractAmt}
else
0

 

I currently have a Dates Table which has no relationships to my Fact table. 

My slicer is YEAR/MONTH is replacing the CurrentPeriodStart in the Crystal formula.

 

Within my fact table i want to apply the measure at row level on each job record.  Below is a sample of the data:-

 

Screenshot 2022-05-04 193713.png

 

Would apprechiate any help on how about i would re construct this as its causing me a few headaches now.

 

Many Thanks

 

Alex

2 REPLIES 2
v-yalanwu-msft
Community Support
Community Support

Hi, @AlexDawson111 ;

Is your problem solved? If so, kindly mark the proper reply as a solution to help others having the similar issue and close the case. If not, let me know and I'll try to help you further.


Best Regards,
Community Support Team _ Yalan Wu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

v-yalanwu-msft
Community Support
Community Support

Hi, @AlexDawson111 ;

Try it.

measure =
IF (
    MAX ( [urvPMContractAnalysisDD_WithPCOEstCost.Mth] )
        < MAX ( [?CurrentPeriodStart] ),
    IF (
        MAX ( [urvPMContractAnalysisDD_WithPCOEstCost.ProjMth] )
            < MAX ( [?CurrentPeriodStart] ),
        MAX ( urvPMContractAnalysisDD_WithPCOEstCost.ProjDollars ),
        MAX ( urvPMContractAnalysisDD_WithPCOEstCost.ContractAmt )
    ),
    0
)

If not right,Can you post sample data as text and expected output?


Best Regards,
Community Support Team _ Yalan Wu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.