Hi,

I need help in making a chart.

Below I described the problem in the excel sheet.


I have a data table with three columns (Start_date, End_date and Time_cost)

data_table.png

I want to plot this data in the chart as follows.
The Time_cost is to be divided by the number of days in which the Project occurs and placed in individual days in which it occurs. Just like in the Excel chart below

chart.png

For better understanding, I put everything in an excel file

Link to file http://gofile.me/74fh2/cc0521h8J 

 

I am asking for help in solving this problem

 

 

 

2 ACCEPTED SOLUTIONS
amitchandak
Super User
Super User

@amiskow , refer these approches

 

Measure way
Power BI Dax Measure- Allocate data between Range: https://youtu.be/O653vwLTUzM


Tables way
https://amitchandak.mediumcom/dax-get-all-dates-between-the-start-and-end-date-8f3dac4ff90b
https://amitchandak.medium.com/power-query-get-all-dates-between-the-start-and-end-date-9ad6a84cf5f2

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

View solution in original post

Ashish_Mathur
Super User
Super User

Hi,

Please find attached the PBI file.

Hope this helps.

Ashish_Mathur_0-1693635957241.png

 


Regards,
Ashish Mathur
http://www.ashishmathur.com
https://www.linkedin.com/in/excelenthusiasts/

View solution in original post

4 REPLIES 4
amiskow
Helper I
Helper I

@Ashish_Mathur @amitchandak 

Thank you very much for help. That's exactly what it was about 😊

You are welcome.


Regards,
Ashish Mathur
http://www.ashishmathur.com
https://www.linkedin.com/in/excelenthusiasts/
Ashish_Mathur
Super User
Super User

Hi,

Please find attached the PBI file.

Hope this helps.

Ashish_Mathur_0-1693635957241.png

 


Regards,
Ashish Mathur
http://www.ashishmathur.com
https://www.linkedin.com/in/excelenthusiasts/
amitchandak
Super User
Super User

@amiskow , refer these approches

 

Measure way
Power BI Dax Measure- Allocate data between Range: https://youtu.be/O653vwLTUzM


Tables way
https://amitchandak.mediumcom/dax-get-all-dates-between-the-start-and-end-date-8f3dac4ff90b
https://amitchandak.medium.com/power-query-get-all-dates-between-the-start-and-end-date-9ad6a84cf5f2

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.