Hello,
We have many scheduled reports in Power BI. They have started sending out an hour early today. Assuming due to daylight savings change this past weekend.
The reports are set to run at Pacific Time - but they are not. The dropdown does not state just 'Pacfic Time' but (UTC-08:00) PAcific Time. Is there a way to fix this on the server so we do not have to manually change many scheduled report times twice per year?
Thanks,
Dan
Thanks @GilbertQ - that's pretty bad if we need to change scheduled reports ywice per year. Also, the dropdown option shows PAcific Time - and it's not sending at PAcific Time.
Appreciate your response - have sent in support ticket to Msft.
Hi @dancarr22
As far as I know it is not currently built into the Power BI Scheduled refresh.
You can vote for the idea where at https://ideas.powerbi.com
Or you can use Power Automate to refresh the datasets on a schedule?
Refresh your Power BI dataset using Microsoft Flow | Microsoft Power BI Blog | Microsoft Power BI