Hi All,
We are using deployment pipeline for migrating content to production workspace. I noticed that when we use Paginated report visual inside PBIX file, link doesn't get updated to Target Workspace. In such cases we have to keep updating links manually in PBIX file as we migrate from DEV to UAT to Prod?
Is it a known issue going to be fixed soon?
Please let me know. Thanks!
Solved! Go to Solution.
@abpgupta, this is a known gap that we hope to close by end of this semester- April 22.
any update on this feature?
I am also hoping for an update. It looks like this has been out there for a while. This is desperately needed as paginated reports become more common. It's unfortunately not practical to deploy the paginated report to production ahead of the report that calls it.
@Nimrod_Shalit is there any update on the ETA for this fix? I am currently promoting a report with a paginated visual through a pipeline and seem to be running into the same issue.
@abpgupta, this is a known gap that we hope to close by end of this semester- April 22.
We are still waiting for this feature to make deployment seamless using deployment pipeline.
I apologize, but this feature didn't happen eventually due to other priorities that took over.
We still don't have a new timeline for when will that happen.
Sure. Idea is to reduce overheads for development and reusing different components for their purpose using single interface. Hope, this is prioritized soon.
Hey @abpgupta ,
from my understanding this behavior is known to the development team, but I'm not aware of any timeline that this will change soon.
I recommend opening an issue on issues.powerbi.com
Regards,
Tom
Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.
User | Count |
---|---|
39 | |
21 | |
21 | |
19 | |
10 |
User | Count |
---|---|
35 | |
35 | |
34 | |
20 | |
14 |