Hello Everyone,

 

I have 4 workspaces which are used in Production. Right now we're implementing Deployment Pipelines and I want to use one Pipeline for the whole process, so we can have one development stage which will send items to 4 different Test Stages and from there each test stage will send items to the corresponding item in the prod stage. Is it possible? If yes, how can I do it?

 

Thanks

 

1 ACCEPTED SOLUTION
SamsonTruong
Super User
Super User

Hi @julsr ,

This currently is not supported natively in Fabric Deployment Pipelines as each stage in the pipeline can only be assigned to a single workspace. As an additional note, if you decide to go the route of multiple pipelines, you will need a separate dev workspace for each pipeline as each workspace can only be assigned to a single pipeline.

Here is some Microsoft Documenation that contains considerations and limitations: https://learn.microsoft.com/en-us/fabric/cicd/deployment-pipelines/assign-pipeline

 

If this helped, please mark it as the solution so others can benefit too. And if you found it useful, kudos are always appreciated.

Thanks,

Samson

 

Connect with me on LinkedIn

Check out my Blog

Going to the European Microsoft Fabric Community Conference? Check out my Session

View solution in original post

3 REPLIES 3
SamsonTruong
Super User
Super User

Hi @julsr ,

This currently is not supported natively in Fabric Deployment Pipelines as each stage in the pipeline can only be assigned to a single workspace. As an additional note, if you decide to go the route of multiple pipelines, you will need a separate dev workspace for each pipeline as each workspace can only be assigned to a single pipeline.

Here is some Microsoft Documenation that contains considerations and limitations: https://learn.microsoft.com/en-us/fabric/cicd/deployment-pipelines/assign-pipeline

 

If this helped, please mark it as the solution so others can benefit too. And if you found it useful, kudos are always appreciated.

Thanks,

Samson

 

Connect with me on LinkedIn

Check out my Blog

Going to the European Microsoft Fabric Community Conference? Check out my Session

Thanks! So I'll need to create one pipeline and one dev and test workspace per Prod Workspace. Sounds like too much work but I'll do it. I don't know if I use the Azure Pipelines will solve this but that's for another thread. Thank you!

Hi @julsr ,

This approach would work for your use case. If you were interested in other CI/CD methodologies in Fabric, below is a link that showcases some sample architectures:

Helpful resources

Announcements
August Power BI Update Carousel

Power BI Monthly Update - August 2025

Check out the August 2025 Power BI update to learn about new features.

August 2025 community update carousel

Fabric Community Update - August 2025

Find out what's new and trending in the Fabric community.