I've noticed when I do the initial load of a incremental refresh Dataflow (30+ minutes), it prevents all other scheduled Dataflows within the same Workspace/Capacity from going through. They all seem to be waiting inline on the new Dataflow.
Is this the expected functionality? Is there a way to allow both those large initial refreshes to succeed AND my scheduled short Dataflow refreshes at the same time?
The only "solution" I've found is to create a 2nd Workspace on a different Capacity and do the initial Dataflow load there. It's not ideal, just a workaround.