Hi community.

 

I have two columns in my excel worksheet with two types of  dates. 

 

#1 starting date of the work

#2 End date of the work.

 

I need to calculate how many days has passed since the work started but the end date must be blank (this means that the work has not finished yet)

 

any ideas?

 

Thanks!

1 ACCEPTED SOLUTION
Washivale
Resolver V
Resolver V

Hi There,

 

you can use following formula to calculate number of days passed since work Started.

 

i am assuming start date is in column B, and End Date is in Column C

 

enter Number of days in Column D as follow

 

=If(C2="", Today()-B2,C2-B2)

 

convert column format to General

 

Explanation 

C2=""  This part of formula will check if end date is blank, if it is blank if condition will return true and below condition will run

 

Today()- B2 : Today() will return todays date and Start date will be substracted from Todays date.

 

if End date is present then C2-B2 will return days passed between Start and End Date.

 

if you dont wish to calculate days for work finished records, you can use below formula

 

=If(C2="", Today()-B2,"")

 

let me know if it works!

 

Thank You

View solution in original post

1 REPLY 1
Washivale
Resolver V
Resolver V

Hi There,

 

you can use following formula to calculate number of days passed since work Started.

 

i am assuming start date is in column B, and End Date is in Column C

 

enter Number of days in Column D as follow

 

=If(C2="", Today()-B2,C2-B2)

 

convert column format to General

 

Explanation 

C2=""  This part of formula will check if end date is blank, if it is blank if condition will return true and below condition will run

 

Today()- B2 : Today() will return todays date and Start date will be substracted from Todays date.

 

if End date is present then C2-B2 will return days passed between Start and End Date.

 

if you dont wish to calculate days for work finished records, you can use below formula

 

=If(C2="", Today()-B2,"")

 

let me know if it works!

 

Thank You

Helpful resources

Announcements
Fabric Data Days is here Carousel

Fabric Data Days 2026

Don't miss out on Data Days, June 15 through August 7. Learn Fabric, Power BI, SQL, AI and more.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.