Hi, im new to Power Bi .
Im trying to generate an S-Curve for resources.
Budget VS Actual using a stacked bar with line for cumulative Units a running total for each.
Im trying to get a running total for Budgeted Units VALUES and a second one for Actual Units VALUES.
With an end result with both sets of values on the chart.
Thanks in advance 🙂
Solved! Go to Solution.
Hi @Anonymous
You can create two measures in the model to calculate the running totals for actual and budget values separately. Add both to Line y-axis on the visual.
Running Total of Actual =
CALCULATE (
SUM ( SampleTable[Value] ),
ALLSELECTED ( SampleTable[Date] ),
SampleTable[Date] <= MAX ( SampleTable[Date] ),
SampleTable[Spreadsheet Field] = "Actual Units"
)
Running Total of Budget =
CALCULATE (
SUM ( SampleTable[Value] ),
ALLSELECTED ( SampleTable[Date] ),
SampleTable[Date] <= MAX ( SampleTable[Date] ),
SampleTable[Spreadsheet Field] = "Budgeted Units"
)
Best Regards,
Community Support Team _ Jing
If this post helps, please Accept it as Solution to help other members find it.
Hi @Anonymous
Use this measure for actual units.
Running Total of Actual =
VAR lastActualDate =
CALCULATE (
MAX ( SampleTable[Date] ),
ALLSELECTED ( SampleTable[Date] ),
SampleTable[Spreadsheet Field] = "Actual Units"
)
RETURN
IF (
MAX ( SampleTable[Date] ) <= lastActualDate,
CALCULATE (
SUM ( SampleTable[Value] ),
ALLSELECTED ( SampleTable[Date] ),
SampleTable[Date] <= MAX ( SampleTable[Date] ),
SampleTable[Spreadsheet Field] = "Actual Units"
),
BLANK ()
)
Best Regards,
Community Support Team _ Jing
If this post helps, please Accept it as Solution to help other members find it.
Is there a way of adapting the expression to have it as a percentage of total units?
Planned % complete Vs Actual % of complete.
Hi @Anonymous
What should be the total (denominator) on every date?
Planned % of complete = (?) / (?)
Hope this helps.
Is it possible as before to stop the Actual % Running only to the max date to prevent the flat cumulative line?
Thanks in advance ,
Really appreciate it.
Hi @Anonymous
You can create two measures in the model to calculate the running totals for actual and budget values separately. Add both to Line y-axis on the visual.
Running Total of Actual =
CALCULATE (
SUM ( SampleTable[Value] ),
ALLSELECTED ( SampleTable[Date] ),
SampleTable[Date] <= MAX ( SampleTable[Date] ),
SampleTable[Spreadsheet Field] = "Actual Units"
)
Running Total of Budget =
CALCULATE (
SUM ( SampleTable[Value] ),
ALLSELECTED ( SampleTable[Date] ),
SampleTable[Date] <= MAX ( SampleTable[Date] ),
SampleTable[Spreadsheet Field] = "Budgeted Units"
)
Best Regards,
Community Support Team _ Jing
If this post helps, please Accept it as Solution to help other members find it.
Thank you so much :).
Is there a way i can modify the code to stop the code from running for the actual units up to a certain date? so i can prevent the to prevent the flat line afterwards. To Try and show a tracking line Budget VS Actual?
Hi @Anonymous
Use this measure for actual units.
Running Total of Actual =
VAR lastActualDate =
CALCULATE (
MAX ( SampleTable[Date] ),
ALLSELECTED ( SampleTable[Date] ),
SampleTable[Spreadsheet Field] = "Actual Units"
)
RETURN
IF (
MAX ( SampleTable[Date] ) <= lastActualDate,
CALCULATE (
SUM ( SampleTable[Value] ),
ALLSELECTED ( SampleTable[Date] ),
SampleTable[Date] <= MAX ( SampleTable[Date] ),
SampleTable[Spreadsheet Field] = "Actual Units"
),
BLANK ()
)
Best Regards,
Community Support Team _ Jing
If this post helps, please Accept it as Solution to help other members find it.
Thank You so much 🙂