Running Total on two sets of Data
Hi, im new to Power Bi .
Im trying to generate an S-Curve for resources.
Budget VS Actual using a stacked bar with line for cumulative Units a running total for each.
Im trying to get a running total for Budgeted Units VALUES and a second one for Actual Units VALUES.
With an end result with both sets of values on the chart.
Thanks in advance 🙂
Hi Anonymous
You can create two measures in the model to calculate the running totals for actual and budget values separately. Add both to Line y-axis on the visual.
Running Total of Actual = CALCULATE ( SUM ( SampleTable[Value] ), ALLSELECTED ( SampleTable[Date] ), SampleTable[Date] <= MAX ( SampleTable[Date] ), SampleTable[Spreadsheet Field] = "Actual Units" )Running Total of Budget = CALCULATE ( SUM ( SampleTable[Value] ), ALLSELECTED ( SampleTable[Date] ), SampleTable[Date] <= MAX ( SampleTable[Date] ), SampleTable[Spreadsheet Field] = "Budgeted Units" )Best Regards,
Community Support Team _ Jing
If this post helps, please Accept it as Solution to help other members find it.Hi Anonymous
Use this measure for actual units.
Running Total of Actual = VAR lastActualDate = CALCULATE ( MAX ( SampleTable[Date] ), ALLSELECTED ( SampleTable[Date] ), SampleTable[Spreadsheet Field] = "Actual Units" ) RETURN IF ( MAX ( SampleTable[Date] ) <= lastActualDate, CALCULATE ( SUM ( SampleTable[Value] ), ALLSELECTED ( SampleTable[Date] ), SampleTable[Date] <= MAX ( SampleTable[Date] ), SampleTable[Spreadsheet Field] = "Actual Units" ), BLANK () )Best Regards,
Community Support Team _ Jing
If this post helps, please Accept it as Solution to help other members find it.
7 Replies
- v-jingzhang
Community Support
Hi Anonymous
You can create two measures in the model to calculate the running totals for actual and budget values separately. Add both to Line y-axis on the visual.
Running Total of Actual = CALCULATE ( SUM ( SampleTable[Value] ), ALLSELECTED ( SampleTable[Date] ), SampleTable[Date] <= MAX ( SampleTable[Date] ), SampleTable[Spreadsheet Field] = "Actual Units" )Running Total of Budget = CALCULATE ( SUM ( SampleTable[Value] ), ALLSELECTED ( SampleTable[Date] ), SampleTable[Date] <= MAX ( SampleTable[Date] ), SampleTable[Spreadsheet Field] = "Budgeted Units" )Best Regards,
Community Support Team _ Jing
If this post helps, please Accept it as Solution to help other members find it.- AnonymousNot applicable
Thank you so much :).
Is there a way i can modify the code to stop the code from running for the actual units up to a certain date? so i can prevent the to prevent the flat line afterwards. To Try and show a tracking line Budget VS Actual?
- v-jingzhang
Community Support
Hi Anonymous
Use this measure for actual units.
Running Total of Actual = VAR lastActualDate = CALCULATE ( MAX ( SampleTable[Date] ), ALLSELECTED ( SampleTable[Date] ), SampleTable[Spreadsheet Field] = "Actual Units" ) RETURN IF ( MAX ( SampleTable[Date] ) <= lastActualDate, CALCULATE ( SUM ( SampleTable[Value] ), ALLSELECTED ( SampleTable[Date] ), SampleTable[Date] <= MAX ( SampleTable[Date] ), SampleTable[Spreadsheet Field] = "Actual Units" ), BLANK () )Best Regards,
Community Support Team _ Jing
If this post helps, please Accept it as Solution to help other members find it.
- AnonymousNot applicable
Is there a way of adapting the expression to have it as a percentage of total units?
Planned % complete Vs Actual % of complete.
- v-jingzhang
Community Support
Hi Anonymous
What should be the total (denominator) on every date?
Planned % of complete = (?) / (?)
- AnonymousNot applicable
Hope this helps.
Is it possible as before to stop the Actual % Running only to the max date to prevent the flat cumulative line?
Thanks in advance ,
Really appreciate it.