Afternoon Everyone.
I was wondering if someone can help me. At present P6 in the company I work for is not directly connected to PowerBi.
I want to create a planning dashboard using data from P6. I have set up a report in P6 which downloads it to an excel file which I point to PowerBi.
As an example below I have several columns which contain information, and then to the right date columns. These date column headers will change as and when the schedule changes.
Previously I use to
However, the issue is if the date changes (which it does, or additional dates are added) the re-fresh throws up an error.
Someone previoiusly told me to pivot the date columns first then promote the headers, but this doesn't appear to work and pull in the data?
| Client | Project Number | CTR Status | Date | Date |
Hi @Anonymous ,
What error will you get?
Check whether below thread will help:
Solved: Promote headers from a specific row - Microsoft Power BI Community
Best Regards,
Kelly
Did I answer your question? Mark my post as a solution!
Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.
If you love stickers, then you will definitely want to check out our community sticker challenge, Barcelona edition!
Check out the July 2026 Power BI update to learn about new features.