Afternoon Everyone.
I was wondering if someone can help me. At present P6 in the company I work for is not directly connected to PowerBi.
I want to create a planning dashboard using data from P6. I have set up a report in P6 which downloads it to an excel file which I point to PowerBi.
As an example below I have several columns which contain information, and then to the right date columns. These date column headers will change as and when the schedule changes.
Previously I use to
However, the issue is if the date changes (which it does, or additional dates are added) the re-fresh throws up an error.
Someone previoiusly told me to pivot the date columns first then promote the headers, but this doesn't appear to work and pull in the data?
| Client | Project Number | CTR Status | Date | Date |
Hi @Anonymous ,
What error will you get?
Check whether below thread will help:
Solved: Promote headers from a specific row - Microsoft Power BI Community
Best Regards,
Kelly
Did I answer your question? Mark my post as a solution!