Hello All,

 

Can someone advise how to accomplish this using power query? budget is set, committed and spent amounts are dynamic. we could commit/spend less or more. I would like the cost column to reflect properly.

 

Thank you!

 

budgetcommitedspent cost 
 $100.00 $    50.00 $   40.00 $  60.00
 $100.00 $    50.00 $   60.00 $  40.00
 $100.00 $    60.00 $   70.00 $  30.00
 $100.00 $  100.00 $100.00 $        -  0

 

2 REPLIES 2
v-frfei-msft
Community Support
Community Support

Hi @SalimHoud ,

 

Refering to your data, we can get the cost column by

= [budget] - [spent]

 

Then what is your excepted reuslt?

 

Community Support Team _ Frank
If this post helps, then please consider Accept it as the solution to help the others find it more quickly.

I would like to also get the cost amount even if either of the committed or spent columns are blank. I have mitigated this temporary by copying the data over until spent amount is changed at the end of the month to recalculate.

Helpful resources

Announcements
FabCon and SQLCon Barcelona 2026

FabCon & SQLCon – Barcelona 2026

Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.

Fabric Community Sticker Design Challenge Barcelona Carousel

Fabric Community Sticker Challenge - Barcelona 2026

If you love stickers, then you will definitely want to check out our community sticker challenge, Barcelona edition!

July Power BI Update Carousel

Power BI Monthly Update - July 2026

Check out the July 2026 Power BI update to learn about new features.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.