March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early bird discount ends December 31.
Register NowBe one of the first to start using Fabric Databases. View on-demand sessions with database experts and the Microsoft product team to learn just how easy it is to get started. Watch now
I have a Power BI report. In that I need to calculate the 'remaining work capacity' for each date as below.
1. I have a measure that gives 'total remaining work hours', say 500 hours.
2. I have another measure that gives 'max capacity' per day, say 16 hours
3. The 'remaining work capacity' for first 10 days will be equal to 'max capacity'. 16 hours in this case.
4. The 'remaining work capacity' for the next 10 days should be 90% of the 'max capacity'. That is 14.4 hours in this case.
5. The 'remaining work capacity' for the next 10 days should be 90% from the previous calculated 'remaining work capacity. 12.96 hours in this case.
6. Likewise, in each 10 days I need to reduce 10% from the previously calculated 'remaining work capacity'
7. 'remaining work capacity' should set to zero, when the summation of the 'remaining work capacity' reached 'total remaining work hours' (500 hours in this case).
Please guide me to create a measure for calculating 'remaining work capacity'. Thank you.
Solved! Go to Solution.
Hi @v-yiruan-msft ,
Thank you for your sugestions. I was able to solve the issue using POWER function. Also here I am using GENERATESERIES function for getting total work hours calculated upto given date.
My measure logic is as below
Best regards,
Chanaka H
Hi @chanakah ,
You can refer the following links to get it:
Solved: Re: Previous Row Calculation including last calcul... - Microsoft Fabric Community
Solved: Recursive calculation - Microsoft Fabric Community
Previous Value (“Recursion”) in DAX – Greg Deckler
If the above one can't help you, please provide some raw data in your tables (exclude sensitive data) with Text format and your expected result with backend logic and special examples. It would be helpful to find out the solution. You can refer the following links to share the required info:
How to provide sample data in the Power BI Forum
And It is better if you can share a simplified pbix file. You can refer the following link to upload the file to the community. Thank you.
How to upload PBI in Community
Best Regards
Hi @v-yiruan-msft ,
Thank you for your sugestions. I was able to solve the issue using POWER function. Also here I am using GENERATESERIES function for getting total work hours calculated upto given date.
My measure logic is as below
Best regards,
Chanaka H
Hi @chanakah ,
It's glad to hear that your problem has been resolved. And thanks a lot for sharing your solution here. Could you please mark your post as Answered? It will help the others in the community find the solution easily if they face the same problem as yours.
Best Regards
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount!