How to calculate project progress using start date and end date
Solved! Go to Solution.
Hi, @Ykankam
Please try formulas like:
Percentage% =
VAR a =
CALCULATE (
COUNTROWS ( 'Table' ),
FILTER ( 'Table', 'Table'[Project] = EARLIER ( 'Table'[Project] ) )
)
VAR b =
CALCULATE (
COUNTROWS ( 'Table' ),
FILTER (
'Table',
'Table'[Project] = EARLIER ( 'Table'[Project] )
&& 'Table'[Due Status] = "Not Overdue"
)
)
RETURN
b / a
or measure
Percentage1% =
VAR a =
CALCULATE (
COUNTROWS ( 'Table' ),
FILTER ( ALLSELECTED('Table'), 'Table'[Project] = max( 'Table'[Project] ) )
)
VAR b =
CALCULATE (
COUNTROWS ( 'Table' ),
FILTER (
ALLSELECTED('Table'),
'Table'[Project] = MAX( 'Table'[Project] )
&& 'Table'[Due Status] = "Not Overdue"
)
)
RETURN
b/a+0
If it doesn't work, please share a sample file and expected result for further research.
Best Regards,
Community Support Team _ Eason
From the image above. I have a list of projects with start date and end date. Each project has a status.
Now I want a column that will calculate the aggregated completion rate(percentage) for each project base on the start date and end date.
Hi, @Ykankam
Please try formulas like:
Percentage% =
VAR a =
CALCULATE (
COUNTROWS ( 'Table' ),
FILTER ( 'Table', 'Table'[Project] = EARLIER ( 'Table'[Project] ) )
)
VAR b =
CALCULATE (
COUNTROWS ( 'Table' ),
FILTER (
'Table',
'Table'[Project] = EARLIER ( 'Table'[Project] )
&& 'Table'[Due Status] = "Not Overdue"
)
)
RETURN
b / a
or measure
Percentage1% =
VAR a =
CALCULATE (
COUNTROWS ( 'Table' ),
FILTER ( ALLSELECTED('Table'), 'Table'[Project] = max( 'Table'[Project] ) )
)
VAR b =
CALCULATE (
COUNTROWS ( 'Table' ),
FILTER (
ALLSELECTED('Table'),
'Table'[Project] = MAX( 'Table'[Project] )
&& 'Table'[Due Status] = "Not Overdue"
)
)
RETURN
b/a+0
If it doesn't work, please share a sample file and expected result for further research.
Best Regards,
Community Support Team _ Eason
@v-easonf-msft @VahidDM thank you both. It worked.
How do create a dax formula to show all projects startinng next month and another one to show all projects ending this month?
Your question is general without any details, check these links and add more details:
https://community.powerbi.com/t5/Desktop/Progress-Tracker/m-p/1250192
https://community.powerbi.com/t5/Desktop/Create-Progress-Tacker/m-p/2184039
If this post helps, please consider accepting it as the solution to help the other members find it more quickly.
Appreciate your Kudos!!