Hi
I have the below scenario based on today being 2nd March
| Project | Project Start | Project Finish | AFC | Physical Complete | Actuals | Remaining weeks | EV | CPI | ETC |
| A | 01/01/2020 | 31/07/2020 | 20000 | 0.1 | 1900 | 21 | 2000 | 1.052632 | 19000 |
| B | 01/02/2020 | 30/09/2020 | 30000 | 0.2 | 4000 | 30 | 800 | 0.2 | 20000 |
| C | 01/12/2019 | 30/04/2020 | 10000 | 0.7 | 7000 | 8 | 4900 | 0.7 | 10000 |
| D | 01/07/2020 | 31/12/2020 | 20000 | 0 | 0 | 26 | 0 | 1 | 20000 |
I'm looking to generate a forecast based on the above Estimate To Complete (ETC) by flat spreading it from the Monday of the current date to the end of the project (preferably ignoring holidays)!
Any help greatly appreciated, even pointing me to a relevant article.
Solved! Go to Solution.
After trying lots of search terms, I typed "powerquery split value between two dates" and found this...
https://community.powerbi.com/t5/Desktop/Splitting-Values-between-months-of-two-dates/td-p/180075
After trying lots of search terms, I typed "powerquery split value between two dates" and found this...
https://community.powerbi.com/t5/Desktop/Splitting-Values-between-months-of-two-dates/td-p/180075
Hi @Anonymous ,
Is this resolved case your expected result? If is, you could accept your reply to make users find it more quickly.
Check out the November 2025 Power BI update to learn about new features.