Hi,
I am trying to calculate weekly workload for the team.
Eg: When a developer plans to complete a Task in 3 weeks (07/06/2020 to 07/24/2020) then his work load should be distributed to 3 weeks (i.e. 60/3 = 20 hours/Week), so he has 20 hours of work for next three weeks.
Raw Data
| Name | Work Load | Start Date | End Date | Scheduled Hours |
| James | Build | 7/6/2020 | 7/24/2020 | 60 |
| James | Planning | 7/13/2020 | 7/24/2020 | 60 |
| James | Planning | 7/13/2020 | 7/17/2020 | 30 |
| James | Bugs | 7/20/2020 | 7/24/2020 | 30 |
| James | Development | 7/27/2020 | 7/31/2020 | 20 |
| Peter | Planning | 7/6/2020 | 7/10/2020 | 50 |
| Peter | Testing | 7/13/2020 | 7/31/2020 | 90 |
| Peter | Bugs | 7/20/2020 | 7/24/2020 | 10 |
| Henry | Planning | 7/6/2020 | 7/10/2020 | 20 |
| Henry | Analyze | 7/13/2020 | 7/17/2020 | 40 |
| Henry | Bugs | 7/20/2020 | 7/24/2020 | 40 |
| Henry | Testing | 7/6/2020 | 7/31/2020 | 80 |
Additional Info:
You Can find an example of a solution in this github, which essentially uses the following Measure:
******************************************
Deliveriung the expected result (Your example Final Output had a mistake with james, who only had 20h workload in Week 23):
Hope this helps.
Vote for your favorite vizzies from the Power BI World Championship submissions!
If you love stickers, then you will definitely want to check out our Community Sticker Challenge!
Check out the January 2026 Power BI update to learn about new features.
| User | Count |
|---|---|
| 64 | |
| 56 | |
| 43 | |
| 20 | |
| 17 |
| User | Count |
|---|---|
| 123 | |
| 108 | |
| 44 | |
| 32 | |
| 26 |