Table Layout Design, Production Schedule

Hello, I have an issue with creating an appropriate table in Power BI, which is meant to serve as a production schedule for the upcoming days on a specific machine, outlining the next production run for each day and shift. I kindly request assistance in designing such a table. The data will be sourced from an Excel file, but I am uncertain about how to structure the table layout within Power BI.

I am attaching an example of how the production schedule table should look in Power BI.

 

production plan.png

1 ACCEPTED SOLUTION
Anonymous
Not applicable

Hi @Patrick90 ,

I created a sample pbix file(see the attachment), please check if that is what you want.

1. Create two dimension tables as below screenshot

Dimension table: MachineProductionDimension table: MachineProduction

Dimension table: SieDimension table: Sie

2. Create a measure as below to get the next production

NextProductionP = 
VAR _selmachine =
    SELECTEDVALUE ( 'MachineProduction'[Machine] )
VAR _selprod =
    SELECTEDVALUE ( 'MachineProduction'[Production] )
VAR _selsei =
    SELECTEDVALUE ( Sie[Sie] )
VAR _selshift =
    SELECTEDVALUE ( 'Plan'[Shift] )
RETURN
    CALCULATE (
        MAX ( 'Plan'[Next production] ),
        FILTER (
            'Plan',
            'Plan'[Machine] = _selmachine
                && SEARCH ( _selsei, 'Plan'[Start], 1, 0 ) > 0
        )
    )

3. Create a matrix visual as below screenshot

vyiruanmsft_0-1692598497829.png

Best Regards

View solution in original post

1 REPLY 1
Anonymous
Not applicable

Hi @Patrick90 ,

I created a sample pbix file(see the attachment), please check if that is what you want.

1. Create two dimension tables as below screenshot

Dimension table: MachineProductionDimension table: MachineProduction

Dimension table: SieDimension table: Sie

2. Create a measure as below to get the next production

NextProductionP = 
VAR _selmachine =
    SELECTEDVALUE ( 'MachineProduction'[Machine] )
VAR _selprod =
    SELECTEDVALUE ( 'MachineProduction'[Production] )
VAR _selsei =
    SELECTEDVALUE ( Sie[Sie] )
VAR _selshift =
    SELECTEDVALUE ( 'Plan'[Shift] )
RETURN
    CALCULATE (
        MAX ( 'Plan'[Next production] ),
        FILTER (
            'Plan',
            'Plan'[Machine] = _selmachine
                && SEARCH ( _selsei, 'Plan'[Start], 1, 0 ) > 0
        )
    )

3. Create a matrix visual as below screenshot

vyiruanmsft_0-1692598497829.png

Best Regards

Helpful resources

Announcements
Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

October Power BI Update Carousel

Power BI Monthly Update - October 2025

Check out the October 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors