Table Layout Design, Production Schedule

Hello, I have an issue with creating an appropriate table in Power BI, which is meant to serve as a production schedule for the upcoming days on a specific machine, outlining the next production run for each day and shift. I kindly request assistance in designing such a table. The data will be sourced from an Excel file, but I am uncertain about how to structure the table layout within Power BI.

I am attaching an example of how the production schedule table should look in Power BI.

 

production plan.png

1 ACCEPTED SOLUTION
Anonymous
Not applicable

Hi @Patrick90 ,

I created a sample pbix file(see the attachment), please check if that is what you want.

1. Create two dimension tables as below screenshot

Dimension table: MachineProductionDimension table: MachineProduction

Dimension table: SieDimension table: Sie

2. Create a measure as below to get the next production

NextProductionP = 
VAR _selmachine =
    SELECTEDVALUE ( 'MachineProduction'[Machine] )
VAR _selprod =
    SELECTEDVALUE ( 'MachineProduction'[Production] )
VAR _selsei =
    SELECTEDVALUE ( Sie[Sie] )
VAR _selshift =
    SELECTEDVALUE ( 'Plan'[Shift] )
RETURN
    CALCULATE (
        MAX ( 'Plan'[Next production] ),
        FILTER (
            'Plan',
            'Plan'[Machine] = _selmachine
                && SEARCH ( _selsei, 'Plan'[Start], 1, 0 ) > 0
        )
    )

3. Create a matrix visual as below screenshot

vyiruanmsft_0-1692598497829.png

Best Regards

View solution in original post

1 REPLY 1
Anonymous
Not applicable

Hi @Patrick90 ,

I created a sample pbix file(see the attachment), please check if that is what you want.

1. Create two dimension tables as below screenshot

Dimension table: MachineProductionDimension table: MachineProduction

Dimension table: SieDimension table: Sie

2. Create a measure as below to get the next production

NextProductionP = 
VAR _selmachine =
    SELECTEDVALUE ( 'MachineProduction'[Machine] )
VAR _selprod =
    SELECTEDVALUE ( 'MachineProduction'[Production] )
VAR _selsei =
    SELECTEDVALUE ( Sie[Sie] )
VAR _selshift =
    SELECTEDVALUE ( 'Plan'[Shift] )
RETURN
    CALCULATE (
        MAX ( 'Plan'[Next production] ),
        FILTER (
            'Plan',
            'Plan'[Machine] = _selmachine
                && SEARCH ( _selsei, 'Plan'[Start], 1, 0 ) > 0
        )
    )

3. Create a matrix visual as below screenshot

vyiruanmsft_0-1692598497829.png

Best Regards

Helpful resources

Announcements
Join our Fabric User Panel

Join our Fabric User Panel

Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.