Hi,
I have the below code in M that gives the number of days between the start date and end date (it works fine):
[EndDate]-[StartDate]
But if I try to subtract "1" then I get an error:
[EndDate]-[StartDate]-1
I assume it's because [EndDate] and [StartDate] are stored as dates but "1" is an integar? Please do you know how to fix?
Thanks,
CM
Solved! Go to Solution.
Replace 1 by: #duration(1,0,0,0)
Replace 1 by: #duration(1,0,0,0)
Vote for your favorite vizzies from the Power BI World Championship submissions!
If you love stickers, then you will definitely want to check out our Community Sticker Challenge!
Check out the January 2026 Power BI update to learn about new features.
| User | Count |
|---|---|
| 58 | |
| 52 | |
| 40 | |
| 17 | |
| 16 |
| User | Count |
|---|---|
| 111 | |
| 109 | |
| 40 | |
| 33 | |
| 26 |