Hello,
I have two tables as follow:
Table: Calendar
Column: "Date" which contains a formula "Calendar = CALENDARAUTO(3)"
Table: UK holiday
| Date | is_working_day |
| 01/04/2018 | 0 |
| 02/04/2018 | 0 |
| 03/04/2018 | 1 |
| 04/04/2018 | 1 |
| 05/04/2018 | 1 |
| 06/04/2018 | 1 |
| 07/04/2018 | 0 |
| 08/04/2018 | 0 |
| 09/04/2018 | 1 |
When I try to create a relationship and link by Date in both tables, I have a circular dependency problem. Is there a way to fix that?
Thanks,
Ricky
Solved! Go to Solution.
I've seen that circular dependency error before. When creating the relationship, select the UK Holiday table first (top of the relationship), and select the calculated Calendar table second.
Here's a pbix file with your sample data and the relationship created:
https://github.com/ssugar/PowerBICommunity/raw/master/community-sol-264607.pbix
Yup, it looks like it might be. It seems to occur whenever I try to create a relationship with a calculated table on top.
Cheers,
Scott
I've seen that circular dependency error before. When creating the relationship, select the UK Holiday table first (top of the relationship), and select the calculated Calendar table second.
Here's a pbix file with your sample data and the relationship created:
https://github.com/ssugar/PowerBICommunity/raw/master/community-sol-264607.pbix
Check out the May 2026 Power BI update to learn about new features.
Sign up to receive a private message when registration opens and key events begin.
If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.
| User | Count |
|---|---|
| 25 | |
| 24 | |
| 22 | |
| 19 | |
| 18 |
| User | Count |
|---|---|
| 43 | |
| 42 | |
| 41 | |
| 21 | |
| 21 |