Need help with this logic

Hello Everyone, I am trying to create logic but failed to do. 
I need to create a Status Column. In which there should be rows/options i.e "On-Time", "Late", "Released"
"On-Time"= 

NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
    [Release Date] <= [Baseline_EndDate], "On-Time"
"Late"=
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
    [Release Date] > [Baseline_EndDate] ||
    ISBLANK(Project_v2_w_LW_PPC[Release Date]) && [Baseline_EndDate] < TODAY(), "Late"
"Released"= 
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
    [Release Date] <= [Baseline_EndDate || 
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
    [Release Date] > [Baseline_EndDate]

(Basically, if any row has a Release Date Then It will be considered as Released)

 

The issue is with the Released logic because of overlapping conditions with On-Time and Late. How to write this codition correctly?

Thank You,
Ajit

19 REPLIES 19
Kedar_Pande
Super User
Super User

@ajitsahoo8338 You can try:

Status = 
SWITCH(
TRUE(),
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])), "Released",
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) && Project_v2_w_LW_PPC[Release Date] <= Project_v2_w_LW_PPC[Baseline_EndDate], "On-Time",
(
ISBLANK(Project_v2_w_LW_PPC[Release Date]) && Project_v2_w_LW_PPC[Baseline_EndDate] < TODAY()
) ||
(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) && Project_v2_w_LW_PPC[Release Date] > Project_v2_w_LW_PPC[Baseline_EndDate]
), "Late",

BLANK()
)

This structure ensures each row fits into exactly one category without overlap.

 

💌 If this helped, a Kudos 👍 or Solution mark would be great! 🎉
Cheers,
Kedar
Connect on LinkedIn

Hello @Kedar_Pande This is not working

ajitsahoo8338
Helper III
Helper III

Hello @Bibiano_Geraldo and @Uzi2019  

My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection it should show Late and For Released Selection, it should show those rows which have a release date

ajitsahoo8338_0-1729076449705.png

 

Uzi2019
Super User
Super User

HI @ajitsahoo8338 

 

Can you share the sample data with expected output??

 

It would be better working with data instead of just a logic.

 

you can share the simple excel file screenshot for better understanding.

 

 

Don't forget to give thumbs up and accept this as a solution if it helped you!!!

Hello @Uzi2019 

My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection it should show Late and For Released Selection, it should show those rows which have a release date.

ajitsahoo8338_1-1729076765067.png

 

Hi,
Based on your table, you need to create two calculated columns and you will have to add two slicers to your report:

Column for released status:
ReleasedStatus =
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])),
"Released",
BLANK()
)


Column for On time and Late Status:

 

OnTimeOrLate =
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
Project_v2_w_LW_PPC[Release Date] <= Project_v2_w_LW_PPC[Baseline_EndDate],
"On-Time",
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
Project_v2_w_LW_PPC[Release Date] > Project_v2_w_LW_PPC[Baseline_EndDate],
"Late",
IF(
ISBLANK(Project_v2_w_LW_PPC[Release Date]),
"Open",
BLANK()
)
)
)

Hi @ajitsahoo8338 

 

Can you add one more staus column of Late/Release/On time. next to your table.???

so that will create logic accordingly..

 

Don't forget to give thumbs up and accept this as a solution if it helped you!!!

ajitsahoo8338_0-1729076280288.png

My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection it should show Late and For Released Selection, it should show those rows which have a release date

 

Project NumberActivity NumberTask NameResourceBaseline EndDateRelease Date
2263000Long Lead ReleaseMECHANICAL8/16/2024 0:008/16/2024 0:00
2273000Long Lead ReleaseMECHANICAL8/16/2024 0:008/16/2024 0:00
1003000Manuals CompleteTECH6/18/2024 0:006/18/2024 0:00
2273001GA Tasks/Initial BOMMECHANICAL9/13/2024 0:009/20/2024 0:00
2253002GA Initial BOM ReleaseMECHANICAL7/29/2024 0:008/16/2024 0:00
2263002 BOM ReleaseMECHANICAL9/13/2024 0:00 
2203002Initial BOMMECHANICAL2/29/2024 0:003/29/2024 0:00
723002l Comp Long LeadMECHANICAL5/31/2024 0:005/10/2024 0:00
1313002Paint SchemeMECHANICAL6/21/2024 0:005/2/2024 0:00
1313003Stop KitELECTRICAL5/31/2024 0:005/31/2024 0:00
2253003MA GroupMECHANICAL9/17/2024 0:00 
1323004Power RevisionELECTRICAL7/29/2024 0:007/30/2024 0:00

My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection it should show Late and For Released Selection, it should show those rows which have a release date

ajitsahoo8338
Helper III
Helper III

Hello @Bibiano_Geraldo  Thank you for your response. After using your DAX I am only getting On-Time and Late. 

ajitsahoo8338_0-1729074730360.png

 

Could you please share a sample of your table? Please dont share sensitive data.

Note:
The released status will only appear if all other status are not satisfied.

Hello @Bibiano_Geraldo 

My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection,it should show Late and For Released Selection, it should show those rows which have a release date

ajitsahoo8338_0-1729076703939.png

 

 

Hello @Bibiano_Geraldo and @Uzi2019 My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection it should show Late and For Released Selection, it should show those rows which have a release date.

ajitsahoo8338_0-1729076337215.png

 

Hi @ajitsahoo8338 

Please write status in front of that table. like this

Uzi2019_0-1729148795994.png

 

so will implement the logic accordingly.

 

 

Don't forget to give thumbs up and accept this as a solution if it helped you!!!

Hello @Uzi2019 

In The Slicer, There should be there option to select. Released, on time and Late. If I select Released then it should show all On-Time rows and Late Rows which have a Release Date. For On-Time Selection, it should show all on-time rows and for late selection, it should show all late rows.

ajitsahoo8338_1-1729155641617.png

 

Hello @Uzi2019 

In The Slicer, There should be three option to select. Released, on time and Late. If I select Released then it should show all On-Time rows and Late Rows which have a Release Date. For On-Time Selection, it should show all on-time rows and for late selection, it should show all late rows.

ajitsahoo8338_1-1729155641617.png

 

Bibiano_Geraldo
Super User
Super User

Hi,

Try the following DAX:

If this answer help you, please make it as solution.

Status =
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
Project_v2_w_LW_PPC[Release Date] <= Project_v2_w_LW_PPC[Baseline_EndDate],
"On-Time",
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
Project_v2_w_LW_PPC[Release Date] > Project_v2_w_LW_PPC[Baseline_EndDate],
"Late",
IF(
ISBLANK(Project_v2_w_LW_PPC[Release Date]) &&
Project_v2_w_LW_PPC[Baseline_EndDate] < TODAY(),
"Late",
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])),
"Released",
BLANK()
)
)
)
)

Hello @Bibiano_Geraldo  Thank you for your response. After using your DAX I am only getting On-Time and Late. 

ajitsahoo8338_0-1729074916214.png

 

Hello @Bibiano_Geraldo  After using you DAX. I am only geting Late and On-Time not Released.

ajitsahoo8338_0-1729074841295.png

 

Helpful resources

Announcements
November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors
Top Kudoed Authors