Forum Discussion
Need help with this logic
Can you share the sample data with expected output??
It would be better working with data instead of just a logic.
you can share the simple excel file screenshot for better understanding.
- ajitsahoo83381 year agoHelper III
Project Number Activity Number Task Name Resource Baseline EndDate Release Date 226 3000 Long Lead Release MECHANICAL 8/16/2024 0:00 8/16/2024 0:00 227 3000 Long Lead Release MECHANICAL 8/16/2024 0:00 8/16/2024 0:00 100 3000 Manuals Complete TECH 6/18/2024 0:00 6/18/2024 0:00 227 3001 GA Tasks/Initial BOM MECHANICAL 9/13/2024 0:00 9/20/2024 0:00 225 3002 GA Initial BOM Release MECHANICAL 7/29/2024 0:00 8/16/2024 0:00 226 3002 BOM Release MECHANICAL 9/13/2024 0:00 220 3002 Initial BOM MECHANICAL 2/29/2024 0:00 3/29/2024 0:00 72 3002 l Comp Long Lead MECHANICAL 5/31/2024 0:00 5/10/2024 0:00 131 3002 Paint Scheme MECHANICAL 6/21/2024 0:00 5/2/2024 0:00 131 3003 Stop Kit ELECTRICAL 5/31/2024 0:00 5/31/2024 0:00 225 3003 MA Group MECHANICAL 9/17/2024 0:00 132 3004 Power Revision ELECTRICAL 7/29/2024 0:00 7/30/2024 0:00 My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection it should show Late and For Released Selection, it should show those rows which have a release date
- ajitsahoo83381 year agoHelper III
My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection it should show Late and For Released Selection, it should show those rows which have a release date
- ajitsahoo83381 year agoHelper III
Hello Uzi2019
My data looks like this. I want to create a visual table like this and add a status slicer. From that slicer, If I select On-Time then it should show On-Time rows and For Late selection it should show Late and For Released Selection, it should show those rows which have a release date.
- Uzi20191 year agoCommunity Champion
Can you add one more staus column of Late/Release/On time. next to your table.???
so that will create logic accordingly..
- Bibiano_Geraldo1 year agoSuper User
Hi,
Based on your table, you need to create two calculated columns and you will have to add two slicers to your report:
Column for released status:
ReleasedStatus =
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])),
"Released",
BLANK()
)Column for On time and Late Status:
OnTimeOrLate =
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
Project_v2_w_LW_PPC[Release Date] <= Project_v2_w_LW_PPC[Baseline_EndDate],
"On-Time",
IF(
NOT(ISBLANK(Project_v2_w_LW_PPC[Release Date])) &&
Project_v2_w_LW_PPC[Release Date] > Project_v2_w_LW_PPC[Baseline_EndDate],
"Late",
IF(
ISBLANK(Project_v2_w_LW_PPC[Release Date]),
"Open",
BLANK()
)
)
)