Measure Possible Context Issue

Hi there,

 

The following measure is causing my visual to "...exceed the available resources"

 

 

CF_ReviewStatusDays = 
var v_formatting =
    SWITCH(
        TRUE(),              
        isblank(max('Document Review (Workflow)'[Actual Completion Date])),0,
        max('Document Review (Workflow)'[Days (before/after) Scheduled Completion])>=1                      //1-4 days before scheduled completion date
            && max('Document Review (Workflow)'[Days (before/after) Scheduled Completion])<5, 1,
        max('Document Review (Workflow)'[Days (before/after) Scheduled Completion])>=5, 2,                  //5+ days before scheduled completion date
        max('Document Review (Workflow)'[Days (before/after) Scheduled Completion])<0, -1                   //Overdue
    )
    RETURN
    v_formatting

 

 

The measure is trying to provide some coding to support conditional formatting on my table.

 

If the completion date is blank then return 0

If the number of days until scheduled completion is between 1-4 then return 1

If the number of days until scheduled completion is greater than 5 then return 2

and if the number of days until scheduled completion is negative return -1

 

Is the problem associated with mixing my date table with numbers or a context problem?  Please help.

 

The model is as follow:

 

msa_007_0-1716879222443.png

 

Any help appreciated.  thanks.

 

2 REPLIES 2
msa_007
Frequent Visitor

Hi @amitchandak,

 

Thanks for your reply.

 

I think you didn't see the date component of the dax, and I think that was the main issue I was having.  Any ideas on that?  Many thanks for your help.

amitchandak
Super User
Super User

@msa_007 ,Try

 

CF_ReviewStatusDays =
var _max = max('Document Review (Workflow)'[Days (before/after) Scheduled Completion])
var v_formatting =
SWITCH(
TRUE(),
isblank(_max),0,
_max <0, -1 , //Overdue
_max <5, 1,
_max>=5, 2 //5+ days before scheduled completion date

)
RETURN
v_formatting

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

Helpful resources

Announcements
Fabric Data Days is here Carousel

Fabric Data Days 2026

Don't miss out on Data Days, June 15 through August 7. Learn Fabric, Power BI, SQL, AI and more.

May Power BI Update Carousel

Power BI Monthly Update - May 2026

Check out the May 2026 Power BI update to learn about new features.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.