KPI report problem

Hey guys !

 

I have a big problem. I created a cumulative curve based on %task finished. It works, but my reference curve doesn't go all the way to 100%... Some values are just not taken into account and I don't know why. If you could enlighten me, it would be super nice !

Some values are just not taken into account...Some values are just not taken into account...

 

 

Cumulative curves, reference in greenCumulative curves, reference in green

 

 

 

If you have any ideas...

1 ACCEPTED SOLUTION
v-sihou-msft
Microsoft Employee
Microsoft Employee

@Negral75

 

In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.

 

See my sample below:

 

Capture.PNG

 

Regards,

View solution in original post

1 REPLY 1
v-sihou-msft
Microsoft Employee
Microsoft Employee

@Negral75

 

In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.

 

See my sample below:

 

Capture.PNG

 

Regards,

Helpful resources

Announcements
Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount!

Jan25PBI_Carousel

Power BI Monthly Update - January 2025

Check out the January 2025 Power BI update to learn about new features in Reporting, Modeling, and Data Connectivity.

Jan NL Carousel

Fabric Community Update - January 2025

Find out what's new and trending in the Fabric community.