KPI report problem

Hey guys !

 

I have a big problem. I created a cumulative curve based on %task finished. It works, but my reference curve doesn't go all the way to 100%... Some values are just not taken into account and I don't know why. If you could enlighten me, it would be super nice !

Some values are just not taken into account...

 

 

Cumulative curves, reference in green

 

 

 

If you have any ideas...

  • Negral75

     

    In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.

     

    See my sample below:

     

     

    Regards,