KPI report problem
Hey guys !
I have a big problem. I created a cumulative curve based on %task finished. It works, but my reference curve doesn't go all the way to 100%... Some values are just not taken into account and I don't know why. If you could enlighten me, it would be super nice !
Some values are just not taken into account...
Cumulative curves, reference in green
If you have any ideas...
In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.
See my sample below:
Regards,
1 Reply
- v-sihou-msftMicrosoft Employee
In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.
See my sample below:
Regards,