Hey guys !
I have a big problem. I created a cumulative curve based on %task finished. It works, but my reference curve doesn't go all the way to 100%... Some values are just not taken into account and I don't know why. If you could enlighten me, it would be super nice !
Some values are just not taken into account...
Cumulative curves, reference in green
If you have any ideas...
Solved! Go to Solution.
In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.
See my sample below:
Regards,
In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.
See my sample below:
Regards,
A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.
Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.
| User | Count |
|---|---|
| 46 | |
| 31 | |
| 29 | |
| 15 | |
| 15 |
| User | Count |
|---|---|
| 58 | |
| 56 | |
| 38 | |
| 21 | |
| 21 |