Hey guys !
I have a big problem. I created a cumulative curve based on %task finished. It works, but my reference curve doesn't go all the way to 100%... Some values are just not taken into account and I don't know why. If you could enlighten me, it would be super nice !
Some values are just not taken into account...
Cumulative curves, reference in green
If you have any ideas...
Solved! Go to Solution.
In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.
See my sample below:
Regards,
In your scenario, I don't know how you define your TOTALADVANCEMENT measure. I think you should calculate the cumulative total first, then divide by the TOTALADVANCEMENT.
See my sample below:
Regards,
This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.
Check out the June 2025 Power BI update to learn about new features.
User | Count |
---|---|
67 | |
61 | |
52 | |
36 | |
35 |
User | Count |
---|---|
84 | |
74 | |
56 | |
45 | |
44 |