Skip to main content
cancel
Showing results for 
Search instead for 
Did you mean: 

Next up in the FabCon + SQLCon recap series: The roadmap for Microsoft SQL and Maximizing Developer experiences in Fabric. All sessions are available on-demand after the live show. Register now

Reply
AllanBerces
Post Prodigy
Post Prodigy

IF Negative value

Hi good day can someone help me on my calculated column or can i do the same in PQ.
 - IF the Progress is Negative and the Work % equal to 100 then used the Plan value, IF the Work % is not equal to 100 then copy the Progress value

 

AllanBerces_0-1749086199625.png

RESULT

AllanBerces_1-1749086398323.png

 

Thank you

3 ACCEPTED SOLUTIONS
Ritaf1983
Super User
Super User

Hi @AllanBerces 
You can add custom column with the formula :
if [Progress]<0 and [#"Work %"]=100 then [Plan]
else [Progress]

Ritaf1983_0-1749089163412.png

Please note :
You don't need a column if the goal is to put the calculation in visualization, you can just create a measure like :

test measure =

if( max('Table'[Progress])<0 && max('Table'[Work %])=100,sum('Table'[Plan]),sum('Table'[Progress]))

More information about differenses between calculated columns vs measures here :
https://www.sqlbi.com/articles/calculated-columns-and-measures-in-dax/

If this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.


The pbix with the example is attached

Regards,
Rita Fainshtein | Microsoft MVP
https://www.linkedin.com/in/rita-fainshtein/
Blog : https://www.madeiradata.com/profile/ritaf/profile

View solution in original post

@AllanBerces 

you can try this

 

= if [Progress]<0 and [#"Work%"]=100 then [Plan] else if [#"Work%"] = 100 then [Progress] else if [#"Work%"]=0 then [Plan] else [Progress]

 

11.png





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!




View solution in original post

Hi again , then the formula will be :
PQ:

You can add custom column with the formula :
if [Work%]<0 =0 then [Plan]
else [Progress]

 Dax :

Test measure =

if( max('Table'[Work %])=0,sum('Table'[Plan]),sum('Table'[Progress]))

If this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.

Regards,
Rita Fainshtein | Microsoft MVP
https://www.linkedin.com/in/rita-fainshtein/
Blog : https://www.madeiradata.com/profile/ritaf/profile

View solution in original post

6 REPLIES 6
Ritaf1983
Super User
Super User

Hi @AllanBerces 
You can add custom column with the formula :
if [Progress]<0 and [#"Work %"]=100 then [Plan]
else [Progress]

Ritaf1983_0-1749089163412.png

Please note :
You don't need a column if the goal is to put the calculation in visualization, you can just create a measure like :

test measure =

if( max('Table'[Progress])<0 && max('Table'[Work %])=100,sum('Table'[Plan]),sum('Table'[Progress]))

More information about differenses between calculated columns vs measures here :
https://www.sqlbi.com/articles/calculated-columns-and-measures-in-dax/

If this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.


The pbix with the example is attached

Regards,
Rita Fainshtein | Microsoft MVP
https://www.linkedin.com/in/rita-fainshtein/
Blog : https://www.madeiradata.com/profile/ritaf/profile

Hi @Ritaf1983 thank you very much for the reply, a follow up query if i want to add new condition (IF the Work % is equal to 0 then copy the Plan Value else Progress Value). Thank you

Hi again , then the formula will be :
PQ:

You can add custom column with the formula :
if [Work%]<0 =0 then [Plan]
else [Progress]

 Dax :

Test measure =

if( max('Table'[Work %])=0,sum('Table'[Plan]),sum('Table'[Progress]))

If this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.

Regards,
Rita Fainshtein | Microsoft MVP
https://www.linkedin.com/in/rita-fainshtein/
Blog : https://www.madeiradata.com/profile/ritaf/profile

Hi @Ritaf1983 @ryan_mayu thank you very much for the reply, working as i need.

you are welcome





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!




@AllanBerces 

you can try this

 

= if [Progress]<0 and [#"Work%"]=100 then [Plan] else if [#"Work%"] = 100 then [Progress] else if [#"Work%"]=0 then [Plan] else [Progress]

 

11.png





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!




Helpful resources

Announcements
New to Fabric survey Carousel

New to Fabric Survey

If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.

FabCon and SQLCon Highlights Carousel

FabCon &SQLCon Highlights

Experience the highlights from FabCon & SQLCon, available live and on-demand starting April 14th.

March Power BI Update Carousel

Power BI Community Update - March 2026

Check out the March 2026 Power BI update to learn about new features.