I am stuck with this scenario. Is it possible to create a week number column wherein the first week consist of 8 days and the 4th or 5th week is 6 days depending on the month? Please see below sample.
Jan 28 to Feb 4 = 1st week
Feb 5 to Feb 11 = 2nd week
Feb 12 to Feb 18 = 3rd week
Feb 19 to feb 24 = 4th week
Feb 25 to Mar 4 = 1st week
Mar 5 to Mar 11 = 2nd week
Mar 12 to 18 = 3rd week
Mar 19 to Mar 25 = 4th week
Mar 26 to 31 = 5th week
an so on...
Thank you in advance.
Hello @MNM,
You can use the DAX function WEEKNUM to achieve this.
Custom Week Number =
VAR DaysInWeek =
IF(
MONTH([Date]) <> MONTH([Date] - 7),
8,
IF(
MONTH([Date]) = 2,
IF(
DAY([Date] - WEEKDAY([Date], 1)) < 28,
8,
IF(
DAY([Date] - WEEKDAY([Date], 1)) > 28,
6,
7
)
),
7
)
)
RETURN
WEEKNUM([Date], 2) +
IF(
WEEKDAY([Date], 2) = 1,
0,
IF(
WEEKDAY([Date], 2) < 5,
1,
IF(
WEEKDAY([Date], 2) + DaysInWeek > 7,
2,
1
)
)
)
Hope this helps. Should you require further assistance, please do not hesitate to reach out.
Hello @Sahir_Maharaj
I tried applying the dax but its not showing the correct week number.
Thank you in advance
Check out the April 2026 Power BI update to learn about new features.
If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.
A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.
| User | Count |
|---|---|
| 45 | |
| 38 | |
| 34 | |
| 21 | |
| 17 |
| User | Count |
|---|---|
| 65 | |
| 63 | |
| 31 | |
| 26 | |
| 25 |