Hi!
I am stuck with this scenario. Is it possible to create a week number column wherein the first week consist of 8 days and the 4th or 5th week is 6 days depending on the month? Please see below sample.
Jan 28 to Feb 4 = 1st week
Feb 5 to Feb 11 = 2nd week
Feb 12 to Feb 18 = 3rd week
Feb 19 to feb 24 = 4th week
Feb 25 to Mar 4 = 1st week
Mar 5 to Mar 11 = 2nd week
Mar 12 to 18 = 3rd week
Mar 19 to Mar 25 = 4th week
Mar 26 to 31 = 5th week
an so on...
Thank you in advance.
2 Replies
- Sahir_MaharajSuper User
Hello MNM,
You can use the DAX function WEEKNUM to achieve this.
Custom Week Number = VAR DaysInWeek = IF( MONTH([Date]) <> MONTH([Date] - 7), 8, IF( MONTH([Date]) = 2, IF( DAY([Date] - WEEKDAY([Date], 1)) < 28, 8, IF( DAY([Date] - WEEKDAY([Date], 1)) > 28, 6, 7 ) ), 7 ) ) RETURN WEEKNUM([Date], 2) + IF( WEEKDAY([Date], 2) = 1, 0, IF( WEEKDAY([Date], 2) < 5, 1, IF( WEEKDAY([Date], 2) + DaysInWeek > 7, 2, 1 ) ) )Hope this helps. Should you require further assistance, please do not hesitate to reach out.
- MNMFrequent Visitor
Hello Sahir_Maharaj
I tried applying the dax but its not showing the correct week number.
Custom Week Number =VAR DaysInWeek =IF(MONTH('Dates'[Date]) <> MONTH('Dates'[Date] - 7),8,IF(MONTH('Dates'[Date]) = 2,IF(DAY('Dates'[Date] - WEEKDAY('Dates'[Date],1)) < 28,8,IF(DAY('Dates'[Date] - WEEKDAY('Dates'[Date],1)) > 28,6,7)),7))RETURNWEEKNUM('Dates'[Date],2) +IF(WEEKDAY('Dates'[Date], 2) = 1,0,IF(WEEKDAY('Dates'[Date], 2) < 5,1,IF(WEEKDAY('Dates'[Date],2) + DaysInWeek > 7,2,1)))Thank you in advance