Helper IV
Helper IV

Create a Calculated table

Hi, I'm new to calculated tables. But I think I need this as my raw dataset is not expressed the way I want it. Therefore I have two questions related to below raw data screenshot:

2018-02-19_15-08-12.jpg

 

 

 

 

 

 

 

 

 

 

 

 

 

 

I would like to build a new table with following type of columns:

1. One type of coloumn which returns the same parameter for instance 'Project code' but it should not return 'distinct' as I have multiple values of these.

 

2. A bit more advanced: Can I create a column which returns the dates in columns C if column B has a specific name like 'Budget approved'. In a nut sheel I would like to have a column named 'Budget approved' and the dates as rows.

 

I'm able to create all this in a pivot table in excel, but I would like to let powerBI handle it instead.

2018-02-19_15-24-24.jpg

 

 

 

 

 

 

Thanks

Kristoffer

1 ACCEPTED SOLUTION

Hi @Kristofferaabo,

 

Could you try the formula below to see if it works? Smiley Happy

Table =
SUMMARIZE (
    'Table1',
    'Table1'[project Code],
    'Table1'[last_name],
    "Budget approved", CALCULATE (
        FIRSTNONBLANK ( 'Table1'[actual_date], 1 ),
        FILTER ( 'Table1', 'Table1'[milestone_name] = "Budget approved" )
    ),
    "Budget submitted", CALCULATE (
        FIRSTNONBLANK ( 'Table1'[actual_date], 1 ),
        FILTER ( 'Table1', 'Table1'[milestone_name] = "Budget submitted" )
    )
)

 

Regards

View solution in original post

4 REPLIES 4
v-ljerr-msft
Microsoft Employee
Microsoft Employee

Hi @Kristofferaabo,

 

If I understand you correctly, you should be able to use the formula below to create a new calculate table to get the expected result in your scenario. Smiley Happy

Table =
SUMMARIZE (
    'Table1',
    'Table1'[project Code],
    'Table1'[last_name],
    "Budget approved", CALCULATE (
        FIRSTNONBLANK ( 'Table1'[actual_date], 1 ),
        FILTER ( 'Table1', 'Table1'[milestone_name] = "Budget approved" )
    )
)

Note: You'll need to replace 'Table1' with your real table name.

 

Regards

Hi @v-ljerr-msft, this is really cool. Exactly what I was looking for. Perhaps a stupid question, But I was trying to include another column as I wanted a couple of these columns in my data (basically because I want to calculate time between each columns).

I tried something lik ethis, but it gives me a "TRUE/FALSE error"

 

Table =
SUMMARIZE (
    'Table1',
    'Table1'[project Code],
    'Table1'[last_name],
    "Budget approved", CALCULATE (
        FIRSTNONBLANK ( 'Table1'[actual_date], 1 ),
        FILTER ( 'Table1', 'Table1'[milestone_name] = "Budget approved" ),
"Budget submitted", CALCULATE (
        FIRSTNONBLANK ( 'Table1'[actual_date], 1 ),
        FILTER ( 'Table1', 'Table1'[milestone_name] = "Budget submitted" )
) )

 

 

Hi @Kristofferaabo,

 

Could you try the formula below to see if it works? Smiley Happy

Table =
SUMMARIZE (
    'Table1',
    'Table1'[project Code],
    'Table1'[last_name],
    "Budget approved", CALCULATE (
        FIRSTNONBLANK ( 'Table1'[actual_date], 1 ),
        FILTER ( 'Table1', 'Table1'[milestone_name] = "Budget approved" )
    ),
    "Budget submitted", CALCULATE (
        FIRSTNONBLANK ( 'Table1'[actual_date], 1 ),
        FILTER ( 'Table1', 'Table1'[milestone_name] = "Budget submitted" )
    )
)

 

Regards

YOU ARE WIZARD! Thanks

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.