Create Progress Tacker

Hello, I am fairly new to PowerBI and am wondering if the following is possible. I have a list of projects with their start and end dates and am looking to create a bar chart tracker that can shows the number of active projects by each week throughout the year. I was able to create a weeknumber column but the projects only show up on the week they start and do not accumulate over time. 

 

Data format I have:

 

Project NameProject Start DateProject End Date
1January 1, 2021January 15, 2021
2January 5, 2021January 30, 2021
3January 7, 2021February 10, 2021
4January 10, 2021February 2, 2021

 

 

Desired Output Layout

      
     
     
     
Number of Active Projects    
     
     
 12345
 Week Number

 

 

Thanks in advance for any help.

1 ACCEPTED SOLUTION
PhilipTreacy
Super User
Super User

Hi @Anonymous 

 

Download sample PBIX file with the following data/chart

 

Using a measure like this will give you what you need by Week Number.

Active Projects By WeekNum = CALCULATE(COUNTROWS('Data'), FILTER(ALL('Data'), WEEKNUM('Data'[Project Start Date],1) <= SELECTEDVALUE(DateTable[WeekNumber]) && WEEKNUM('Data'[Project End Date],1) >= SELECTEDVALUE('DateTable'[WeekNumber])))

projects2.png

 

This is using the Week Number form the DateTable.  See PBIX file above.

 

Regards

 

Phil

 

 



Did I answer your question? Then please mark my post as the solution.
If I helped you, click on the Thumbs Up to give Kudos.


Blog :: YouTube Channel :: Connect on Linkedin


Proud to be a Super User!


View solution in original post

2 REPLIES 2
PhilipTreacy
Super User
Super User

Hi @Anonymous 

 

Download sample PBIX file with the following data/chart

 

Using a measure like this will give you what you need by Week Number.

Active Projects By WeekNum = CALCULATE(COUNTROWS('Data'), FILTER(ALL('Data'), WEEKNUM('Data'[Project Start Date],1) <= SELECTEDVALUE(DateTable[WeekNumber]) && WEEKNUM('Data'[Project End Date],1) >= SELECTEDVALUE('DateTable'[WeekNumber])))

projects2.png

 

This is using the Week Number form the DateTable.  See PBIX file above.

 

Regards

 

Phil

 

 



Did I answer your question? Then please mark my post as the solution.
If I helped you, click on the Thumbs Up to give Kudos.


Blog :: YouTube Channel :: Connect on Linkedin


Proud to be a Super User!


Anonymous
Not applicable

Thank you @PhilipTreacy this is exactly what I needed!

Helpful resources

Announcements
Fabric Data Days is here Carousel

Fabric Data Days 2026

Don't miss out on Data Days, June 15 through August 7. Learn Fabric, Power BI, SQL, AI and more.

May Power BI Update Carousel

Power BI Monthly Update - May 2026

Check out the May 2026 Power BI update to learn about new features.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.