6 years agoHelper II
Contains Formula
Hi there I have a series of custom columns example: Concept (result is either pass fail or query) Initiative (result is either pass fail or query) Project (result is either pass fail or query) ...
- Anonymous6 years ago
Hi Nikki ,
Create a Calculated Column
Status = SWITCH ( TRUE (), 'Table'[Concept] = "Fail" || 'Table'[Initiative] = "Fail" || 'Table'[Project] = "Fail" || 'Table'[Brief] = "Fail", "Fail", 'Table'[Concept] = "Query" || 'Table'[Initiative] = "Query" || 'Table'[Project] = "Query" || 'Table'[Brief] = "Query", "Query", "Pass" )
Regards,Harsh Nathani
Appreciate with a Kudos!! (Click the Thumbs Up Button)Did I answer your question? Mark my post as a solution!
Anonymous
6 years agoNot applicable
Hi Nikki ,
Create a Calculated Column
Status =
SWITCH (
TRUE (),
'Table'[Concept] = "Fail"
|| 'Table'[Initiative] = "Fail"
|| 'Table'[Project] = "Fail"
|| 'Table'[Brief] = "Fail", "Fail",
'Table'[Concept] = "Query"
|| 'Table'[Initiative] = "Query"
|| 'Table'[Project] = "Query"
|| 'Table'[Brief] = "Query", "Query",
"Pass"
)
Regards,
Harsh Nathani
Appreciate with a Kudos!! (Click the Thumbs Up Button)
Did I answer your question? Mark my post as a solution!
- Nikki6 years agoHelper II
Hi Again
my formula worked:
Concept Stage Status =SWITCH (TRUE (),'Projects'[Concept Status] = "Fail"|| 'Projects'[P20 Status] = "Fail"|| 'Projects'[Pact Status] = "Fail"|| 'Projects'[SPOE Status] = "Fail"|| 'Projects'[Seed Funding Artefact Status] = "Fail","Fail",'Projects'[Concept Status] = "Query"|| 'Projects'[P20 Status] = "Query"|| 'Projects'[Pact Status] = "Query"|| 'Projects'[Seed Funding Artefact Status] = "Query"|| 'Projects'[SPOE Status] = "Query", "Query","Pass")but now i have another challenge. I need to only show a result (pass, query or fail) only if the project is in the concept stage. or it has already been thru that stage.I have another table that flags the stage which is concept, evaluate, design, build , closei reapted the above formula for each stage result. but if i am in evaluate i shoudl see a result for concept and evaluate but not for design build close.i have another table that keeps track of what stage the project is in called projectstage (it has either in progress or completed. for each 5 stages)what is best way to achieve this ?- AntrikshSharma6 years agoCommunity ChampionYou could use RELATED or LOOKUPVALUE to bring the value from other tables virtually for the duration of the calculation and check if it matches a condition.