Burn-Up Chart for Project % Completion

Hi everyone,

 

Trying to do something that probably isn’t all that difficult but for whatever reason isn’t coming naturally to me.

 

I’d like to create a “burn-up” chart to show the rate required to achieve 100% completion of all work items by a specified date.  Some example data, assuming I get a reading once every 2 days or so (and it doesn’t start at 0 because I didn’t start gathering data until after it was in motion).

 

Date

% Completed

% Desired

5/3/2019

16.10%

 

5/5/2019

16.10%

 

5/6/2019

17.50%

 

5/8/2019

17.50%

 

5/10/2019

17.50%

 

5/12/2019

18.90%

 

5/15/2019

18.90%

 

5/16/2019

19.50%

 

5/18/2019

 

23.1%

5/20/2019

 

26.82%

5/22/2019

 

30.48%

5/24/2019

 

34.14%

 

And let’s just say I had to get to 100% by 6/30.  Would want to project a column/measure that showed the % complete required on each day (basically, the rate required) to make that goal.  I’m not sure if the numbers I have there are exactly right, but hopefully you get the idea.  Note that currently the % completed in my chart is a calculated measure.  Any suggestions?

1 ACCEPTED SOLUTION
v-juanli-msft
Community Support
Community Support

Hi @brianlehr 

1.Create a date table

Date table = CALENDARAUTO()

Create relationship as below

4.png

 

2. in Sheet3, create measures as below

lastdate = MAXX(FILTER(ALL(Sheet3),[% Completed]<>BLANK()),Sheet3[Date])

desireddate = DATE(2019,6,30)

period = DATEDIFF([lastdate]+1,[desireddate],DAY)/2

last percent = 
CALCULATE([% Completed],FILTER(ALL(Sheet3),Sheet3[Date]=[lastdate]))

rate = (1-[last percent])/[period]

start = IF(MAX('Date table'[Date])=[lastdate]+2,[last percent]+[rate])

data_modified =
VAR num =
    DATEDIFF ( [lastdate] + 2, MAX ( 'Date table'[Date] ), DAY ) / 2
RETURN
    IF (
        num = INT ( num )
            && MAX ( 'Date table'[Date] ) <= [desireddate],
        IF ( MAX ( 'Date table'[Date] ) = [lastdate] + 2, [start], [rate] ),
        BLANK ()
    )

% Desired =
VAR desireddata =
    SUMX (
        FILTER (
            ALL ( 'Date table' ),
            'Date table'[Date] >= [lastdate] + 2
                && 'Date table'[Date] <= [desireddate]
                && 'Date table'[Date]
                    <= MAX ( 'Date table'[Date] ) + 1
        ),
        [data_modified]
    )
RETURN
    IF ( [data_modified] <> BLANK (), desireddata, BLANK () )

final = IF([% Desired]=BLANK(),[% Completed],[% Desired])

5.png6.png

Best Regards
Maggie

 

Community Support Team _ Maggie Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

5 REPLIES 5
v-juanli-msft
Community Support
Community Support

Hi @brianlehr 

1.Create a date table

Date table = CALENDARAUTO()

Create relationship as below

4.png

 

2. in Sheet3, create measures as below

lastdate = MAXX(FILTER(ALL(Sheet3),[% Completed]<>BLANK()),Sheet3[Date])

desireddate = DATE(2019,6,30)

period = DATEDIFF([lastdate]+1,[desireddate],DAY)/2

last percent = 
CALCULATE([% Completed],FILTER(ALL(Sheet3),Sheet3[Date]=[lastdate]))

rate = (1-[last percent])/[period]

start = IF(MAX('Date table'[Date])=[lastdate]+2,[last percent]+[rate])

data_modified =
VAR num =
    DATEDIFF ( [lastdate] + 2, MAX ( 'Date table'[Date] ), DAY ) / 2
RETURN
    IF (
        num = INT ( num )
            && MAX ( 'Date table'[Date] ) <= [desireddate],
        IF ( MAX ( 'Date table'[Date] ) = [lastdate] + 2, [start], [rate] ),
        BLANK ()
    )

% Desired =
VAR desireddata =
    SUMX (
        FILTER (
            ALL ( 'Date table' ),
            'Date table'[Date] >= [lastdate] + 2
                && 'Date table'[Date] <= [desireddate]
                && 'Date table'[Date]
                    <= MAX ( 'Date table'[Date] ) + 1
        ),
        [data_modified]
    )
RETURN
    IF ( [data_modified] <> BLANK (), desireddata, BLANK () )

final = IF([% Desired]=BLANK(),[% Completed],[% Desired])

5.png6.png

Best Regards
Maggie

 

Community Support Team _ Maggie Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

@v-juanli-msft This is great!  Usually I'm able to follow along, but I will admit that some of this lost me on first glance, but it seems to work.  I'll need to study this more to understand.  Thanks!

parry2k
Super User
Super User

@brianlehr what would be the calculation for %desired?



Subscribe to the @PowerBIHowTo YT channel for an upcoming video on List and Record functions in Power Query!!

Learn Power BI and Fabric - subscribe to our YT channel - Click here: @PowerBIHowTo

If my solution proved useful, I'd be delighted to receive Kudos. When you put effort into asking a question, it's equally thoughtful to acknowledge and give Kudos to the individual who helped you solve the problem. It's a small gesture that shows appreciation and encouragement! ❤


Did I answer your question? Mark my post as a solution. Proud to be a Super User! Appreciate your Kudos 🙂
Feel free to email me with any of your BI needs.

Sorry, not sure I understand the question?   The % desired is what I want to generate as a "burnup".

 

So to get the sample numbers shown there, I worked out what the % required increase for every data measurement period would be.

 

I assume 6/30 which was 22 "2-day periods" from the last date with data, so I think you'd need about 3.6% per each period to reach 100% by 6/30.

@parry2k and community -- any suggestions?

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.