Hi,
I am trying to create a line that follows progress on 43 purchase orders (POs) in a project. Each purchase order has a date for baseline, a date for forecast, and a date for actual achieved. I want to create a graph illustrating the trend in each of these. The plan will be updated continually until all POs are placed. I want a graph that looks more or less like this.
Instead og managing to get the graph I want, I used a work-around where I actually created three separate graphs that I placed above eachother, where all Axes are completely fixed. This is, of course, only a temporary remedy.
How can I create this graph without having to create three separate graphs? I currently have the three fields, where I am getting aggregates by creating a Quick Measure for running totals of each field. When I try to add a second field to the Values of any of the graphs, it stops show aggregate info, and instead looks like this:
Any tips would be great!
Hello @Espen1515
Are you using this type of visualisation ? Because on my version of PBI I can add as many measure I want to create graph
If you are already using it, can you provide us a sample of your data (sample + table name + field name) so that we try to do what you are looking for ?
Quentin
How can I send sample data to you. When I try to respond I don't see an Add Attachment button. Only an Insert Link button that links to a URL. How can I send you data from my desktop?
Copy paste as a excel table 🙂
| Activity | Package number | Activity Description | Package Description | BL Finish | Early Finish | Curr act. Finish |
| JRBC50304 | BC503 | Issue Inquiry | Accoustic Cassettes / Walls | 29.03.2018 | ||
| JRBC50310 | BC503 | Purchase Agrmt issued to supplier | Accoustic Cassettes / Walls | 07.06.2018 | ||
| JRBE53104 | BE531 | Issue Inquiry | Power, Instrument & Telecom Cables | 29.05.2018 | ||
| JRBE53110 | BE531 | Purchase Agrmt issued to supplier | Power, Instrument & Telecom Cables | 07.08.2018 | ||
| JRBE53204 | BE532 | Issue Inquiry | General Electric Bulk | 29.10.2018 | ||
| JRBE53210 | BE532 | Purchase Agrmt issued to supplier | General Electric Bulk | 07.01.2019 | ||
| JRBE53304 | BE533 | Issue Inquiry | Cable Trays, Ladders & Accessories | 29.08.2018 | ||
| JRBE53310 | BE533 | Purchase Agrmt issued to supplier | Cable Trays, Ladders & Accessories | 07.11.2018 | ||
| JRBE53704 | BE537 | Issue Inquiry | Multi Cable Transits (MCT) | 29.09.2018 | ||
| JRBE53710 | BE537 | Purchase Agrmt issued to supplier | Multi Cable Transits (MCT) | 08.12.2018 | ||
| JRBE54104 | BE541 | Issue Inquiry | Junction Boxes | 29.11.2018 | ||
| JRBE54110 | BE541 | Purchase Agrmt issued to supplier | Junction Boxes | 07.02.2019 | ||
| JRBE54304 | BE543 | Issue Inquiry | Heat Tracing | 29.11.2018 | ||
| JRBE54310 | BE543 | Purchase Agrmt issued to supplier | Heat Tracing | 07.02.2019 | ||
| JRBE54504 | BE545 | Issue Inquiry | Cable Glands | 29.03.2019 | ||
| JRBE54510 | BE545 | Purchase Agrmt issued to supplier | Cable Glands | 07.06.2019 | ||
| JRBE54704 | BE547 | Issue Inquiry | Push Buttons and Socket Outlets | 29.03.2019 | ||
| JRBE54710 | BE547 | Purchase Agrmt issued to supplier | Push Buttons and Socket Outlets | 07.06.2019 | ||
| JRBE55504 | BE555 | Issue Inquiry | Lighting Fixtures | 29.03.2019 | ||
| JRBE55510 | BE555 | Purchase Agrmt issued to supplier | Lighting Fixtures | 07.06.2019 | ||
| JRBI68404 | BI684 | Issue Inquiry | Instr. Tubing and Compression Fittings | 01.03.2019 | ||
| JRBI68410 | BI684 | Purchase Agrmt issued to supplier | Instr. Tubing and Compression Fittings | 10.05.2019 | ||
| JRBL74104 | BL741 | Issue Inquiry | Carbon Steel Pipe/Fittings/Flanges | 16.03.2018 | 16.03.2018 | 16.03.2018 |
| JRBL74110 | BL741 | Purchase Agrmt issued to supplier | Carbon Steel Pipe/Fittings/Flanges | 04.05.2018 | 09.05.2018 | |
| JRBL74304 | BL743 | Issue Inquiry | Duplex/Super Duplex Pipe/Fittings/Flanges | 16.03.2018 | 16.03.2018 | 16.03.2018 |
| JRBL74310 | BL743 | Purchase Agrmt issued to supplier | Duplex/Super Duplex Pipe/Fittings/Flanges | 04.05.2018 | 09.05.2018 | |
| JRBL74404 | BL744 | Issue Inquiry | 316 L & 6Mo Pipe/Fittings/Flanges | 16.03.2018 | 16.03.2018 | 16.03.2018 |
| JRBL74410 | BL744 | Purchase Agrmt issued to supplier | 316 L & 6Mo Pipe/Fittings/Flanges | 04.05.2018 | 09.05.2018 | |
| JRBL74704 | BL747 | Issue Inquiry | Titanium Pipe/Fittings/Flanges | 16.03.2018 | 16.03.2018 | 16.03.2018 |
| JRBL74710 | BL747 | Purchase Agrmt issued to supplier | Titanium Pipe/Fittings/Flanges | 04.05.2018 | 09.05.2018 | |
| JRBL76904 | BL769 | Issue Inquiry | Mechanical Joints | 17.04.2018 | 14.05.2018 | |
| JRBL76910 | BL769 | Purchase Agrmt issued to supplier | Mechanical Joints | 01.06.2018 | 11.06.2018 | |
| JRBL77504 | BL775 | Issue Inquiry | Pipe Supports | 07.05.2018 | ||
| JRBL77510 | BL775 | Purchase Agrmt issued to supplier | Pipe Supports | 02.07.2018 | ||
| JRBL77704 | BL777 | Issue Inquiry | Spring Support | 23.10.2018 | ||
| JRBL77710 | BL777 | Purchase Agrmt issued to supplier | Spring Support | 14.12.2018 | ||
| JRBL78004 | BL780 | Issue Inquiry | Fire Nuts, Elastopipe | 04.10.2018 | ||
| JRBL78010 | BL780 | Purchase Agrmt issued to supplier | Fire Nuts, Elastopipe | 08.12.2018 | ||
| JRBL78304 | BL783 | Issue Inquiry | Piping insulation | 29.09.2018 | ||
| JRBL78310 | BL783 | Purchase Agrmt issued to supplier | Piping insulation | 08.12.2018 | ||
| JRBL78504 | BL785 | Issue Inquiry | Bolts And Nuts | 13.06.2018 | ||
| JRBL78510 | BL785 | Purchase Agrmt issued to supplier | Bolts And Nuts | 06.08.2018 | ||
| JRBL79104 | BL791 | Issue Inquiry | Gaskets And Rings | 13.06.2018 | ||
| JRBL79110 | BL791 | Purchase Agrmt issued to supplier | Gaskets And Rings | 06.08.2018 | ||
| JRBL79304 | BL793 | Issue Inquiry | Flow Coding - Piping/HVAC | 14.09.2019 | ||
| JRBL79310 | BL793 | Purchase Agrmt issued to supplier | Flow Coding - Piping/HVAC | 04.09.2019 | ||
| JRBN80104 | BN801 | Issue Inquiry | Structural Steel Plates | 09.03.2018 | 09.03.2018 | 09.03.2018 |
| JRBN80110 | BN801 | Purchase Agrmt issued to supplier | Structural Steel Plates | 13.04.2018 | 18.04.2018 | 20.04.2018 |
| JRBN80304 | BN803 | Issue Inquiry | Rolled Profiles | 16.03.2018 | 16.03.2018 | 16.03.2018 |
| JRBN80310 | BN803 | Purchase Agrmt issued to supplier | Rolled Profiles | 11.05.2018 | 18.05.2018 | |
| JRBN80504 | BN805 | Issue Inquiry | Seamless Tubulars | 16.03.2018 | 23.03.2018 | 23.03.2018 |
| JRBN80510 | BN805 | Purchase Agrmt issued to supplier | Seamless Tubulars | 11.05.2018 | 18.05.2018 | |
| JRBN80704 | BN807 | Issue Inquiry | Welded Tubulars | 23.03.2018 | 23.03.2018 | 23.03.2018 |
| JRBN80710 | BN807 | Purchase Agrmt issued to supplier | Welded Tubulars | 15.05.2018 | 25.05.2018 | |
| JRBN81004 | BN810 | Issue Inquiry | Aluminium Handrail System | 04.07.2018 | 01.06.2018 | |
| JRBN81010 | BN810 | Purchase Agrmt issued to supplier | Aluminium Handrail System | 31.08.2018 | ||
| JRBN81404 | BN814 | Issue Inquiry | Aluminium Punchole Planks & Treads (Gratings) | 07.11.2018 | 08.09.2018 | |
| JRBN81410 | BN814 | Purchase Agrmt issued to supplier | Aluminium Punchole Planks & Treads (Gratings) | 21.12.2018 | 22.10.2018 | |
| JRBN81504 | BN815 | Issue Inquiry | Aluminium Plates & Profiles | 07.11.2018 | 10.06.2018 | |
| JRBN81510 | BN815 | Purchase Agrmt issued to supplier | Aluminium Plates & Profiles | 21.12.2018 | 24.07.2018 | |
| JRBN81704 | BN817 | Issue Inquiry | Stainless Steel Materials | 04.07.2018 | 20.05.2018 | |
| JRBN81710 | BN817 | Purchase Agrmt issued to supplier | Stainless Steel Materials | 31.08.2018 | 17.07.2018 | |
| JRBN81904 | BN819 | Issue Inquiry | Steel Grating, Planks And Treads | 03.08.2018 | ||
| JRBN81910 | BN819 | Purchase Agrmt issued to supplier | Steel Grating, Planks And Treads | 01.10.2018 | ||
| JRBN82104 | BN821 | Issue Inquiry | Fibre Reinforced Polymer Grating and Treads | 21.12.2018 | 22.09.2018 | |
| JRBN82110 | BN821 | Purchase Agrmt issued to supplier | Fibre Reinforced Polymer Grating and Treads | 15.02.2019 | 17.11.2018 | |
| JRBN82804 | BN828 | Issue Inquiry | Paint | 01.03.2018 | ||
| JRBN82810 | BN828 | Purchase Agrmt issued to supplier | Paint | 10.05.2018 | ||
| JRBN83004 | BN830 | Issue Inquiry | Deck Coating | 01.03.2018 | ||
| JRBN83010 | BN830 | Purchase Agrmt issued to supplier | Deck Coating | 10.05.2018 | ||
| JRBS59004 | BS590 | Issue Inquiry | Passive Fire Proofing | 01.03.2018 | ||
| JRBS59010 | BS590 | Purchase Agrmt issued to supplier | Passive Fire Proofing | 10.05.2018 | ||
| JRBT84004 | BT840 | Issue Inquiry | PAGA (Public Adress & Alarm) bulk material | 01.03.2019 | ||
| JRBT84010 | BT840 | Purchase Agrmt issued to supplier | PAGA (Public Adress & Alarm) bulk material | 10.05.2019 | ||
| JRET38104 | ET381 | Issue Inquiry | Telecom Equipment | 01.03.2019 | ||
| JRET38110 | ET381 | Purchase Agrmt issued to supplier | Telecom Equipment | 10.05.2019 | ||
| JRET38504 | ET385 | Issue Inquiry | UHF Radio and Paging System | 01.03.2019 | ||
| JRET38510 | ET385 | Purchase Agrmt issued to supplier | UHF Radio and Paging System | 10.05.2019 | ||
| JRET38604 | ET386 | Issue Inquiry | Entertainment and data outlets | 01.03.2019 | ||
| JRET38610 | ET386 | Purchase Agrmt issued to supplier | Entertainment and data outlets | 10.05.2019 | ||
| JRET38904 | ET389 | Issue Inquiry | CCTV | 01.03.2019 | ||
| JRET38910 | ET389 | Purchase Agrmt issued to supplier | CCTV | 10.05.2019 | ||
| JRET39104 | ET391 | Issue Inquiry | Personell Tracking and munstering appliances | 01.03.2019 | ||
| JRET39110 | ET391 | Purchase Agrmt issued to supplier | Personell Tracking and munstering appliances | 10.05.2019 | ||
| JRET39704 | ET397 | Issue Inquiry | Wireless access network system | 01.03.2019 | ||
| JRET39710 | ET397 | Purchase Agrmt issued to supplier | Wireless access network system | 10.05.2019 | ||
The graphs I showed before had a filter for "Issue Inquiry" on it.
Hi @Espen1515,
So I have tried replicate it with data you have provided.
I have managed to get "something" from the graph as it should look it. However, the main issue is that you need for legend one column which will contain all the statuses (BL, Curr act and Early finish). And as the axis you would need all the dates.
So you need to make columns where every PO will have the start date and all dates before it will be dismissed.
So you are makin a "cube" as it is called for making data models. In this case you can imagine it as basic graph with X, Y and Z coordinates (x,y,z)
So you would have Statuses as the legend (Z coordinate with value 1) X coordinate as the date value and Y coordinate as the count of POs involved.
In this raw data case you have it, but you are missing dates between which is making gaps in the graph.
What you are looking for is to make custom table, where you will collect all POs with Activity description you would like to have as first column. Second column would be the date and third column would be the value for legend.
So you would Have 12 month for each PO and status. In max case 12(months) * 3 (statuses) per PO.
I am sorry, but I am unable to make the formula for that custom table as I am struggling with similiar case myself 😞
Hi @Espen1515,
Can you please share some data so I would be able to replicate the solution?