New Member

undefined

 

Power bi Dax formula required 

 

Can any one help me to get exact days count between two dates (Start & End) excluding Saturday and Sunday and holidays

1 ACCEPTED SOLUTION
tamerj1
Super User
Super User

Hi @RaghavSai 

You can use NETWORKDAYS function with weekend argument 1

View solution in original post

1 REPLY 1
tamerj1
Super User
Super User

Hi @RaghavSai 

You can use NETWORKDAYS function with weekend argument 1

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.

Top Solution Authors