Power bi Dax formula required 

 

Can any one help me to get exact days count between two dates (Start & End) excluding Saturday and Sunday and holidays

1 ACCEPTED SOLUTION
tamerj1
Super User
Super User

Hi @RaghavSai 

You can use NETWORKDAYS function with weekend argument 1

View solution in original post

1 REPLY 1
tamerj1
Super User
Super User

Hi @RaghavSai 

You can use NETWORKDAYS function with weekend argument 1

Helpful resources

Announcements
PBI Sept Update Carousel

Power BI September 2023 Update

Take a look at the September 2023 Power BI update to learn more.

Learn Live

Learn Live: Event Series

Join Microsoft Reactor and learn from developers.

Dashboard in a day with date

Exclusive opportunity for Women!

Join us for a free, hands-on Microsoft workshop led by women trainers for women where you will learn how to build a Dashboard in a Day!

MPPC 2023 PBI Carousel

Power Platform Conference-Power BI and Fabric Sessions

Join us Oct 1 - 6 in Las Vegas for the Microsoft Power Platform Conference.

Top Solution Authors
Top Kudoed Authors