I have a table where multiple people could be assigned to one project, but even if one person's part is complete the whole project is still live until everyone is done. For instance:
Project ID | Staff | Status |
1 | A | Live |
1 | B | Completed |
1 | C | Completed |
2 | D | Completed |
3 | E | Live |
3 | F | Live |
4 | G | Completed |
4 | H | Live |
4 | I | Completed |
4 | J | Live |
In the above case, only project 2 is fully completed as all of the rows for its Status are set to 'Completed'
I'm looking to add another column which says if a project is fully completed or not but I just can't think of the syntax needed.
Any help would be great. Thank you.
Solved! Go to Solution.
@Socrates - Should be something like:
Column =
VAR __Table = SUMMARIZE(FILTER('Table',[ProjectID]=EARLIER([ProjectID])),[Status])
RETURN
IF(MAXX(__Table,[Status])="Completed" && COUNTROWS(__Table)=1,"Completed","Live")
You asked for a calculated column. A measure would be slightly different.
Completed =
var p = Projects[Project ID]
var s = CALCULATETABLE(VALUES(Projects[Status]),ALL(Projects),Projects[Project ID]=p)
return switch(TRUE(),countrows(s)>1,FALSE(),s={"Completed"},TRUE(),FALSE())
@Socrates - Should be something like:
Column =
VAR __Table = SUMMARIZE(FILTER('Table',[ProjectID]=EARLIER([ProjectID])),[Status])
RETURN
IF(MAXX(__Table,[Status])="Completed" && COUNTROWS(__Table)=1,"Completed","Live")
Check out the July 2025 Power BI update to learn about new features.
This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.
User | Count |
---|---|
26 | |
10 | |
10 | |
9 | |
6 |