Forum Discussion
Socrates
6 years agoFrequent Visitor
Set overall status if all tasks completed
I have a table where multiple people could be assigned to one project, but even if one person's part is complete the whole project is still live until everyone is done. For instance: Project I...
- 6 years ago
Socrates - Should be something like:
Column = VAR __Table = SUMMARIZE(FILTER('Table',[ProjectID]=EARLIER([ProjectID])),[Status]) RETURN IF(MAXX(__Table,[Status])="Completed" && COUNTROWS(__Table)=1,"Completed","Live")
Greg_Deckler
Community Champion
6 years agoSocrates - Should be something like:
Column =
VAR __Table = SUMMARIZE(FILTER('Table',[ProjectID]=EARLIER([ProjectID])),[Status])
RETURN
IF(MAXX(__Table,[Status])="Completed" && COUNTROWS(__Table)=1,"Completed","Live")