I have a Sharepoint list with the below format:
| Task ID | Task description | Resource | Days required | Start Date | Projected completion |
| 1 | Task 1 | A | 10 | 2023-01-05 (example) | CALCULATED |
| 2 | Task 2 | B | 20 | 2023-01-02 (example) | CALCULATED |
| 3 | Task 3 | A | 30 | CALCULATED | CALCULATED |
| 4 | Task 4 | B | 40 | CALCULATED | CALCULATED |
| 5 | Task 5 | Unassigned | 10 | CALCULATED | CALCULATED |
This is not a major project but individual service requests which are independent of each other. Each resource has only 5 hours per day to work.
Based on this, I want to auto populate the start and end date of the following tasks. I am stuck at how do I calculate the start and end dates for the tasks that are unassigned? In this case what could be a better approximation to show the completion schedule of all pending tasks that are unassigned
I am new to power BI and still learning DAX . Any help would be appreciated
Solved! Go to Solution.
Hi @Anonymous ,
I have created a simple sample, please refer to my pbix file to see if it helps you.
Create columns.
startdate = MAXX(FILTER(ALL('Table'),'Table'[Resource]=EARLIER('Table'[Resource])),'Table'[Start Date])projectcompletion = var _1= 'Table'[startdate]+'Table'[Days required]
return
IF('Table'[Start Date]=BLANK()&&'Table'[startdate]=BLANK(),BLANK(),_1)
How to Get Your Question Answered Quickly
If it does not help, please provide more details with your desired output and pbix file without privacy information (or some sample data) .
Best Regards
Community Support Team _ Polly
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi @Anonymous ,
I have created a simple sample, please refer to my pbix file to see if it helps you.
Create columns.
startdate = MAXX(FILTER(ALL('Table'),'Table'[Resource]=EARLIER('Table'[Resource])),'Table'[Start Date])projectcompletion = var _1= 'Table'[startdate]+'Table'[Days required]
return
IF('Table'[Start Date]=BLANK()&&'Table'[startdate]=BLANK(),BLANK(),_1)
How to Get Your Question Answered Quickly
If it does not help, please provide more details with your desired output and pbix file without privacy information (or some sample data) .
Best Regards
Community Support Team _ Polly
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!
Check out the October 2025 Power BI update to learn about new features.
| User | Count |
|---|---|
| 8 | |
| 7 | |
| 6 | |
| 5 | |
| 5 |
| User | Count |
|---|---|
| 24 | |
| 11 | |
| 9 | |
| 9 | |
| 8 |