I started getting below error after upgrading the Gateway to the latest version:
Tried limiting the data to only few days as well still doesnt work.
Any idea what could be wrong in the model?
Solved! Go to Solution.
Hi @rgupta18 ,
Check the similar thread below:
https://community.powerbi.com/t5/Service/DM-GWPipeline-Client-MaxPacketLimitReached/td-p/1084035
Best Regards,
Kelly
Did I answer your question? Mark my post as a solution!
Thanks @v-kelly-msft . I saw that post but didn't help. I ended up redoing the report in the updgraded PowerBI desktop version which fixed it.
Hi @rgupta18 ,
Check the similar thread below:
https://community.powerbi.com/t5/Service/DM-GWPipeline-Client-MaxPacketLimitReached/td-p/1084035
Best Regards,
Kelly
Did I answer your question? Mark my post as a solution!
The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!
| User | Count |
|---|---|
| 58 | |
| 56 | |
| 35 | |
| 18 | |
| 14 |