Join us at FabCon Atlanta from March 16 - 20, 2026, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.
Register now!The Power BI Data Visualization World Championships is back! It's time to submit your entry. Live now!
I started getting below error after upgrading the Gateway to the latest version:
Tried limiting the data to only few days as well still doesnt work.
Any idea what could be wrong in the model?
Solved! Go to Solution.
Hi @rgupta18 ,
Check the similar thread below:
https://community.powerbi.com/t5/Service/DM-GWPipeline-Client-MaxPacketLimitReached/td-p/1084035
Best Regards,
Kelly
Did I answer your question? Mark my post as a solution!
Thanks @v-kelly-msft . I saw that post but didn't help. I ended up redoing the report in the updgraded PowerBI desktop version which fixed it.
Hi @rgupta18 ,
Check the similar thread below:
https://community.powerbi.com/t5/Service/DM-GWPipeline-Client-MaxPacketLimitReached/td-p/1084035
Best Regards,
Kelly
Did I answer your question? Mark my post as a solution!
The Power BI Data Visualization World Championships is back! It's time to submit your entry.
Check out the January 2026 Power BI update to learn about new features.
| User | Count |
|---|---|
| 24 | |
| 13 | |
| 10 | |
| 7 | |
| 6 |