I am having trouble converting 2.4km run times, to correctly display data. Example run is 9:56 (min,sec). But when converted to PQ and transform represents as 12:09:56 AM.
Is there way to convert this is PQ to represent mm:ss?
Solved! Go to Solution.
See this one
= [a=Time.From("00:9:56"),b=#duration(0,0,Time.Minute(a),Time.Second(a))][b]
See this one
= [a=Time.From("00:9:56"),b=#duration(0,0,Time.Minute(a),Time.Second(a))][b]
Hi @Sean29 You could try to add a custom column with this code:
= Text.From(Duration.From([YourTimeColumn]), "mm:ss")
Hope this helps!!
If this solved your problem, please accept it as a solution and a kudos!!
Best Regards,
Shahariar Hafiz
I received couldn't convert to Duration error?