I have a simple table (1) that contains a Date column. Then I have a second table (2) that contains all holidays also on Date level.
Is there any chance to determine the number of working days - excluding holidays - between the Date column of the first table and today?
If so, how?
Solved! Go to Solution.
@joshua1990
You need to add a custom column with the following M Code in Table 1.
List.Count(
if
[Date] > Date.From(DateTime.LocalNow())
then
{}
else
List.Select(
List.Difference(
List.Dates(
[Date],
Duration.Days
(
Date.From(DateTime.LocalNow()) - [Date]
) + 1
,
#duration(1, 0, 0, 0)
),
Holidays[Holiday]
),
each Date.DayOfWeek(_,Day.Monday) < 6
)
)
I have attached the file below.
⭕ Subscribe and learn Power BI from these videos
⚪ Website ⚪ LinkedIn ⚪ PBI User Group
| Thanks to the great efforts by MS engineers to simplify syntax of DAX! Most beginners are SUCCESSFULLY MISLED to think that they could easily master DAX; but it turns out that the intricacy of the most frequently used RANKX() is still way beyond their comprehension! |
DAX is simple, but NOT EASY! |
I am trying to apply your solution to a simila problem I am having. I downloaded the attachment and followed your instructions, but it is not working. Can you please explain why you create the _Measures query and how it helps?
thank you,
@joshua1990
You need to add a custom column with the following M Code in Table 1.
List.Count(
if
[Date] > Date.From(DateTime.LocalNow())
then
{}
else
List.Select(
List.Difference(
List.Dates(
[Date],
Duration.Days
(
Date.From(DateTime.LocalNow()) - [Date]
) + 1
,
#duration(1, 0, 0, 0)
),
Holidays[Holiday]
),
each Date.DayOfWeek(_,Day.Monday) < 6
)
)
I have attached the file below.
⭕ Subscribe and learn Power BI from these videos
⚪ Website ⚪ LinkedIn ⚪ PBI User Group
Thanks @Fowmy : Thanks a lot! But what is about the weekends?
I'm sorry that I missed to add this information:
Working days = Mo - Fr
@joshua1990
I added that condition as well also, attached the file after modification. Please check my 1st reply.
⭕ Subscribe and learn Power BI from these videos
⚪ Website ⚪ LinkedIn ⚪ PBI User Group
The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!
Check out the November 2025 Power BI update to learn about new features.
| User | Count |
|---|---|
| 10 | |
| 6 | |
| 5 | |
| 5 | |
| 2 |